Inspection Status: Passed
Inspection History: ENGR Engineering Final
| Date |
Description |
Inspector |
Results |
Comments |
| 10/15/2020 |
ENGR Engineering Final
|
DROBERTS |
Approved |
Entered by DROBERT5 - |
| 10/14/2020 |
ENGR Engineering Final
|
BBENEDON |
Not ready for Inspection |
Entered by JSCHNEI2 - Not ready. Courtesy, unscheduled inspection for Ray at 602-332-7661. Please schedule all required inspections from your development package permit prior to Requesting building final inspections. |
| 10/19/2020 |
ENGR Engineering Final
|
RLEDONNE |
Continued |
Entered by PAHUMAD1 - Continue. Complete all notes from last inspection before calling for final. |
| 10/15/2020 |
ENGR Engineering Final
|
DROBERTS |
Partial Approval |
Entered by DROBERT5 - COMPLETE THE WOR AS SHOWN ON THE APPROVED PLANS, INSTALL HANDRAIL ON THE SAFETY BARRIER AT THE NORTHEAST CONER OF THID BUILDING IN ALL AREAS THAT HAVE A RUNNING SLOPE VALUE GREATER THAN 5%. |
| 10/14/2020 |
ENGR Engineering Final
|
BBENEDON |
Not ready for Inspection |
Entered by JSCHNEI2 - Not ready. Courtesy, unscheduled inspection for Ray at 602-332-7661. Please schedule all required inspections from your development package permit prior to Requesting building final inspections. |
| 10/01/2020 |
ENGR Engineering Final
|
RLEDONNE |
Not ready for Inspection |
Entered by JSCHNEI2 - Not ready.Walk site with GC went over approved plans and some changes. Advise GC to install per approved plans or provide COT approved revisions for all changes. |