Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: DP17-0142

Parcel: 11620134A


Addresses:

875 W CUSHING ST


Inspection Status: Passed

Inspection History: ENGR Engineering Final

Permit Number - DP17-0142

Inspection Description - ENGR Engineering Final

Inspection Status - Passed

Date Description Inspector Results Comments
05/06/2021 ENGR Engineering Final MHERNANDEZ Approved Entered by VLEON1 -
10/03/2019 ENGR Engineering Final DROBERTS Approved Entered by DROBERT5 -
07/18/2019 ENGR Engineering Final BBENEDON Continued Entered by VFLORES1 - Unscheduled progress inspection. There are a couple broken sections of sidewalk at site entrance. Temporary fencing still installed west side of property. Area south of parking areas appears to be on stabilized, there are some stock piles of material, and there is some Erosion along the east bank.
01/23/2019 ENGR Engineering Final DROBERTS Not ready for Inspection Entered by DROBERT5 - CREWS CONTINUE TO WORK THROUGHOUT THE SITE TRYING TO COMPLETE AS MUCH OF THE EXTERIOR WORK THAT THEY CAN. THEY WILL BE SEEKING A TCO FOR THIS SITE ON OR BEFORE2/15/2019 IF POSSIBLE. I WILL TRY TO WALK THE SITE ON 1/24/2019 TO SEE WHAT REMAINING ITEMS WILL CAUSE ME CONCERN BY THE MIDDLE OF NEXT MONTH.
12/18/2018 ENGR Engineering Final BBENEDON Not ready for Inspection Entered by CBELL1 - Asphalt has been installed but is blocked by a temporary fence. There is no walking access from the street to the building.
10/15/2020 ENGR Engineering Final DROBERTS Approved Entered by RSALDAT1 - IS APPROVED
09/17/2019 ENGR Engineering Final DROBERTS Partial Approval Entered by DMERANZ1 - COMPLETE ALL WORK ON THE SITE AS SHOWN ON THE APPROVED PLANS. PROVIDE THE FOLLOWING CLOSEOUT DOCUMENTS: 1) A SET OF APPROVED REVISED DRAWINGS FOR ALL CHANGES THAT HAVE BEEN MADE TO THIS SITE. 2) PROVIDE PDSD WITH A SEALED CERTIFICATION LETTER FROM THE ENGINEER OF RECORD FOR THIS SITE NOTING THAT IT HAS BEEN CONSTRUCTED PER THE APPROVED PLANS. 3) PROVIDE US WITH A COPY OF THE NOTICE OF TERMINATION FROM ADEQ FOR THIS SITE.