Inspection History Details
Inspection Status: Passed
Inspection History: ENGR Grading Final
Permit Number - DP17-0095
Inspection Description - ENGR Grading Final
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/23/2019 | ENGR Grading Final | DROBERTS | Approved | Entered by DROBERT5 - |
08/01/2017 | ENGR Grading Final | DROERTS | Continued | Entered by DROBERT5 - MET WITH AARON BOND FROM SUNDT CORP AOUT THE SITE AND ADVISED THEM THAT THEY NEEDED TO SCHEDULE THE PRE-CON FOR THE SITE EVEN THOUGH THEY HAVE ALREADY BEGUN THE WORK. CURRENTLY THEY HAVE THE TRACK OUT ROCK AT THE ENTRY GATE, AND HAVE WADDLE AROUND MOST OF THE SITE THAT I COULD SEE. |
03/05/2019 | ENGR Grading Final | DROBERTS | Approved | Entered by DROBERT5 - |
03/01/2019 | ENGR Grading Final | RLEDONNE | Continued | Entered by CBELL1 - |
01/23/2019 | ENGR Grading Final | DROBERTS | Continued | Entered by DROBERT5 - |
03/05/2019 | ENGR Grading Final | DROBERTS | Approved | Entered by DROBERT5 - |
03/01/2019 | ENGR Grading Final | RLEDONNE | Partial Approval | Entered by CBELL1 - Complete all work on approved plans. |
02/14/2018 | ENGR Grading Final | DROBERTS | Not ready for Inspection | Entered by DROBERT5 - ASKED TO LOOK AT THE HEADWALL FORMS ADJACENT TO THE WASH ON THE EAST SIDE OF THE PROJECT. PIMA COUNTY INSPECTED IT BEFORE I ARRIVED ON SITE |
03/21/2020 | ENGR Grading Final | DROBERTS | Approved | Entered by DROBERT5 - |
05/02/2019 | ENGR Grading Final | BBENEDON | Continued | Entered by CBELL1 - Contractor is grading north end of Property. Temporary fencing is still in place. Contractor is installing riprap at West basin entry. |
03/05/2019 | ENGR Grading Final | DROBERTS | Approved | Entered by DROBERT5 - |
02/22/2019 | ENGR Grading Final | DROBERTS | Correction Required | Entered by DROBERT5 - STOPPED BY THE SITE TO SEE HOW IT IS LOOKING SINCE THEY WILL BE ASKING FOR FULL TEMPORARY OCCUPANCY NEXT WEEK. IT HAS BEEN NOTED ON THE SOUTH SIDE OF THIS SITE THAT THERE IS SETTLING IN THE BACKFILL MATERIAL OVER PIPES AND AROUND STRUCTURES WITHIN THE ROADWAY ON THE SOUTHSIDE OF THE BUILDING. DEPENDING WHAT THIS IS CAUSED FROM MAY DELAY MY APPROVAL FOR THE FULL TCO NEXT WEEK. THE CONTRACTOR IS WORKING ON TRYING TO DETERMINE WHAT IS HAPPENING TO CREATE THIS ISSUE, BUT HAS BEEN UNABLE TO DETERMINE WHAT IS HAPPENING. AT THIS TIME. I WILL BE MONITORING THIS SITE DAILY NEXT WEEK UNTIL A DETERMINATION IS MADE. |
02/26/2019 | ENGR Grading Final | DROBERTS | Correction Required | Entered by DROBERT5 - I LOOKED OUT ON THE SITE TO SEE WHAT TYPE OF WORK IS STILL NEEDED TO BE COMPLETED PRIOR TO THE REQUEST OF THE TCO CHANGE TO PUBLIC ACCESS. HARDSCAPING AND LANDSCAPING AROUND THE PARKING LOTS IS STILL NEEDED TO BE COMPLETED PRIOR TO THE ACCESS CHANGE. ALL ITEMS THAT NEED TO BE COMPLETED WITH THE USE OF EQUIPMENT NEEDS TO BE COMPLETED PRIOR TO THE CHANGE OF THE CERTIFICATE OF OCCUPANCY STATUS. ALL AREAS UNDER CONSTRUCTION WILL NEED TO BE BLOCKED OFF BY CONSTRUCTION FENCE MATERIAL TO PREVENT ACCESS INTO THOSE AREAS BY THE GENERAL PUBLIC. IT HAS BEEN NOTED SINCE THIS PAST FRIDAY 2/22/2019 THAT THERE IS A DRAINAGE PROBLEM WITH THE STORMDRAINAGE PIPES THAT RUN UNDERNEATH THE ROADWAY ON THE SOUTHSIDE OF THE BUILDING. SETTLING HAS BEEN NOTED IN THE PAVEMMENT, THE CONTRACTOR HAS REMOVED THE PAVEMENT AND THE CONCRETE COLLARS FROM THE AREA BUT HAVE NOT BEEN ABLE TO DETERMINE WHAT IS THE PROBLEM AT THIS TIME. I HAVE ASKED THAT THAT THEY REMOVE ALL OF THE GRATES OFF OF THE DROP INLET STRUCTURE AND THE MANHOLE COVERS TO VERIFY WHAT IS THE PROBLEM AND WHERE IS IT COMING FROM. I WILL BE ASKING THE CONTRACTOR TO FILM THE FULL RUN OF THE PIPE TO DETERMINE WHAT DAMAGE HAS BEEN DONE AND HOW MUCH CLEANING OF THE SYSTEM WILL BE REQUIRED. THIS WILL BE DISCUSSED IN FURTHER DETAIL TOMORROW MORNING AT 8 AM WHEN WE MEET TO REMOVE THE COVERS. |
01/24/2019 | ENGR Grading Final | DROBERTS | Continued | Entered by DROBERT5 - UNABLE TO WALK THIS SITE TODAY, I HAVE RESCHEDULE THIS SITE INSPECTION TO BE COMPLETED ON 1/25/2019 |
01/23/2019 | ENGR Grading Final | DROBERTS | Continued | Entered by DROBERT5 - CREWS CONTINUE TO WORK THROUGHOUT THE SITE TRYING TO COMPLETE AS MUCH OF THE EXTERIOR WORK THAT THEY CAN. THEY WILL BE SEEKING A TCO FOR THIS SITE ON OR BEFORE2/15/2019 IF POSSIBLE. I WILL TRY TO WALK THE SITE ON 1/24/2019 TO SEE WHAT REMAINING ITEMS WILL CAUSE ME CONCERN BY THE MIDDLE OF NEXT MONTH. |
12/04/2018 | ENGR Grading Final | BBENEDON | Continued | Entered by CBELL1 - Courtesy inspection format at 916 200 85 87. Per plan C - 4.0 sidewalks at shipping and receiving East are okay for concrete , however rain drains are required to not dumb on to walkways. The plan shows the splash block on the opposite side of the walkway. Use grading intermediate inspection for trash enclosure inspections |
09/24/2018 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - I WALKED SITE WITH BRIAN . |
07/10/2018 | ENGR Grading Final | DROBERTS | Continued | Entered by DROBERT5 - 1) CREWS CONTINUE TO EXCAVATE AND PLACE FILL MATERIAL FROM THE NORTHWEST CORNER OF THE SITE AND AS NEEDED WITHIN THE BOUNDARIES OF THIS SITE. 2) CONTINUE WORKING ON THE STRUCTURE LOCATED ON THE NORTHSIDE OF THIS SITE. |
06/13/2018 | ENGR Grading Final | DROBERTS | Continued | Entered by DROBERT5 - THE CREWS ARE WORKING ON EXCAVATING MATERIAL FROM THE NORTHWEST AREA OF THE SITE AND PLACING IT INTO THE SOUTHWEST CORNER OF THE SITE. CONTINUAL WORK ON THE BUILDING CONSTRUCTION. |
02/28/2018 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - STORMWATER PIPING INSPECTION PER HIGH LIGHTS ON PAGEC4.0. |
12/12/2017 | ENGR Grading Final | DROBERTS | Continued | Entered by DROBERT5 - WENT THROUGH THE SITE AND MET WITH THE CONTRACTOR AND DISCUSSED THE ISSUES AT HAND. I AM ASKING THE CONTRACTOR TO PROVIDE THIS DEPARTMENT WITH APPROVED DRAWINGS FOR THE NEW AREAS THAT THEY ARE WORKING ON AT THIS TIME THAT ARE NOT SHOWN ON THE APPROVED PLANS. |
11/28/2017 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - met on site with gc and building inspectors for building pre-con. |
10/31/2017 | ENGR Grading Final | DROBERTS | Continued | Entered by DROBERT5 - CREWS COMTIMUE TO REMOVE OLD LANDFILL MATERIAL AND PLACEMENT OF CLEAN FILL INTO THE SOUTHERN PAD AREA. |
10/03/2017 | ENGR Grading Final | DROBERTS | Continued | Entered by DROBERT5 - THE CREWS ARE WORKING IN THE FOLLOWING AREAS AT THIS TIME: 1) REMOVAL OF THE DUMP MATERIAL, HAULING IT OFF TO CITY DUMP FOR THE PROPER DISPOSAL OF ALL MATERIALS. 2) FORMING FOR THE BOX STRUCTURE AT THE SOUTHWESTQUADRANT OF THE SITE. THIS STRUCTURE MAY BE POURED BY THE END OF THE WEEK ONCE ALL THE FORMS HAVE BEEN PLACED. HAULING IN MATERIAL THAT IS BEING UTILIZED AS FILL MATERIAL FOR THE PAD LOCATED ON THE NORTHN PAD OF THIS SITE. |
08/29/2017 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - TALKED TO GC ABOUT THE CHANCE OF BIKE PATH BEING SHUT DOWN. |