Inspection Status: Partial Pass
Inspection History: ENGR Engineering Final
| Date |
Description |
Inspector |
Results |
Comments |
| 05/01/2020 |
ENGR Engineering Final
|
DROBERTS |
Approved |
Entered by DROBERT5 - |
| 05/01/2020 |
ENGR Engineering Final
|
DROBERTS |
Partial Approval |
Entered by RSALDAT1 - IS PARTIAL AT THIS TIME, CALLED RAND TWICE FOR INSPECTION (520) 349-6989 WITH NO RESPONSE. NEED APPROVED REVISED DRAWINGS ON SITE FOR THE FINAL INSPECTION. |
| 04/02/2020 |
ENGR Engineering Final
|
BBENEDON |
Not ready for Inspection |
Entered by SFLORES2 - Provide 9 inches depth at water harvesting areas C, especially at the east end. Steak trees as shown on plant detail. Provide the quantity of small plant shown on your approval plan. Provide long-term bicycle parking, which is noted to be inside the building. Remove construction debris and plastic covering truncated dome‘s. |
| 05/01/2020 |
ENGR Engineering Final
|
DROBERTS |
Approved |