Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: DP16-0200

Parcel: 11712099A


Addresses:

20 S STONE AV


Inspection Status: Passed

Inspection History: ENGR Engineering Final

Permit Number - DP16-0200

Inspection Description - ENGR Engineering Final

Inspection Status - Passed

Date Description Inspector Results Comments
06/30/2020 ENGR Engineering Final DROBERTS Approved Entered by RSALDAT1 - APPROVED
06/26/2020 ENGR Engineering Final BBENEDON Not ready for Inspection Entered by RSALDAT1 - Not ready. Please provide contact information when scheduling inspections. Please schedule all the remaining inspections for your development package permit. Terminate SWPPP if applicable.
07/21/2020 ENGR Engineering Final DROBERTS Approved Entered by DROBERT5 -
07/13/2020 ENGR Engineering Final DROBERTS Partial Approval Entered by RSALDAT1 - IS PARTIAL AT THIS TIME, OBSERVED THE LOOK OF THE CURRENT CRACK REPAIRS ON THE WEST AND NORTH WEST SIDES OF THE BUILDING, THIS LOOKED ACCEPTABLE AT THIS TIME. I HAVE REMINDED THE CONTRACTOR THAT THEY WILL NEED TO CHECK ALL CRACKS ON THIS JOB SITE TOO SEE IF THERE IS ANY MOVEMENT IN THE SIDEWALKS. THEY HAVE BEEN ADVISED THAT ANY SIDEWALK PANEL WITH MORE THAN ONE CRACK, OR SIGNS OF MOVEMENT WILL REQUIRE THAT THEY NEED TO REMOVE AND REPOUR THE DAMAGED SECTIONS. THEY ARE CURRENTLY USING A 2 PART LIQUID EPOXY TO REPAIR THE DAMAGED SECTIONS OF SIDEWALKS.
07/07/2020 ENGR Engineering Final DROBERTS Partial Approval Entered by RSALDAT1 - IS PARTIAL AT THIS TIME, SITE VISIT WITH KEVIN TO LOOK AT WORK COMPLETED AT THIS TIME. THE HANDRAIL HAS BEEN INSTALLED ON THE WEST SIDE OF THE BUILDING BUT IS STILL MISSING ON THE SOUTH SIDE OF THE BUILDING. KEVIN WILL BE CONTACTING THE ARCHITECT FOR CLARIFICATION OF WHAT IS REQUIRED, HE WILL ALSO DISCUSS THIS ISSUE WITH BUILDING OFFICIAL, CLAYTON TREVILLYAN TO GETTING AN OFFICIAL DETERMINATION ON REQUIREMENTS.
07/06/2020 ENGR Engineering Final BBENEDON Not ready for Inspection Entered by JSCHNEI2 - Not ready. Kevin at 480-413-3260
07/02/2020 ENGR Engineering Final BBENNEDON Partial Approval Entered by JSCHNEI2 - Partially approved. Accessible parking and long-term bicycle parking. Is OK. Via remote inspection with Kevin at 480-341-3260
06/30/2020 ENGR Engineering Final DROBERTS Partial Approval Entered by RSALDAT1 - PARTIAL TILL ALL OTHER COMMENTS HAVE BEEN ADDRESSED. NOTED CRACKS IN THE SIDEWALKS AT VARIOUS LOCATIONS THROUGHOUT THIS SITE, MAKE THE NECESSARY REPAIRS OR REMOVE AND REPLACE ALL AREAS THAT CONTAIN MORE THAN 1 CRACK PER PANEL. IF ANY OF THESE AREAS ARE WITHIN THE RIGHT-OF-WAY CONTACT CITY OF TUCSON TRANSPORTATION FOR THEIR RECOMMENDED REPAIR METHOD. ALSO ALONG THE WEST AND SOUTH SIDE OF THE STRUCTURE IT HAS BEEN NOTED THAT THERE ARE 2 SECTIONS OF SIDEWALK THAT NEED HAND RAIL ON BOTH SIDES OF THE SIDEWALK. 1) ON THE SOUTH SIDE OF THE BUILDING THERE IS A SIDEWALK THE EXCEEDS MORE THAN 5% (5% - -7%)IN THE RUNNING SLOPE. THIS AREA SHOULD HAVE HANDRAIL ON BOTH SIDES OF THE SIDEWALK TILL THE SLOPE IS LESS THAN 5%. 2) ON THE WEST SIDE OF THE BUILDING HEADING NORTH FROM THE SOUTH WEST CORNER THERE ARE 2 RAMPS SECTIONS OF SIDEWALK WITH HANDRAIL ALONG THE EAST SIDE OF THE SIDEWALK, HANDRAIL IS NEED ON BOTH SIDES OF SIDEWALK (34” - 38” above the sidewalk)I CHECKED THIS AREA AND FIN IT TO BE 6% TO 7%, I WILL ASK BRIAN BENNEDON TO CHECK THESE AREAS OUT ON 7/1/2020.
06/26/2020 ENGR Engineering Final BBENEDON Not ready for Inspection Entered by RSALDAT1 - Not ready. Please provide contact information when scheduling inspections. Please schedule all the remaining inspections for your development package permit. Terminate SWPPP if applicable.