Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit: DP16-0182

Parcel: 116293360


Addresses:

710 S GREASEWOOD RD

Inspection Status: Passed

Inspection History: ENGR Engineering Final

Date Description Inspector Results Comments
06/18/2020 ENGR Engineering Final DROBERTS Approved Entered by DROBERT5 - THIS SITE IS COMPLETE EXCEPT FOR THE SIDEWALKS AT THE FOLLOWING LOTS 1 - 3, AND 43, THIS WORK IS BEING COMPLETED UNDER THE COMPLETION BOND.
10/03/2019 ENGR Engineering Final BBENEDON Partial Approval Entered by DMERANZ1 - Project appears to be 75% complete. There is construction in progress. Stormwater controls are still in place. Minor erosion issues need to be corrected. There are material stock piles blocking sidewalks and on Street. There is sediment within concrete drainage structures.
03/29/2018 ENGR Engineering Final RLEDONNE Continued Entered by RLEDONN1 - 50% OF LOTS MUST BE COMPLET BEFORE STARTING TO CLOSE DP.
06/07/2017 ENGR Engineering Final RLEDONNE Continued Entered by RLEDONN1 - REBAR IN SIDEWALK SCUPPER BY LOTS#13AND#14 OK.
05/09/2017 ENGR Engineering Final RLEDONNE Continued Entered by RLEDONN1 - SIDEWALK SCUPPER ON NORTH SIDE OF SITE SOUTH LOT #39.
07/23/2020 ENGR Engineering Final DROBERTS Approved Entered by DROBERT5 - ALL WORK IS COMPLETED AT THIS TIME, MINOR MAINTENANCE WORK IS INSPECTED UNDER THE COMBO PERMIT FOR LOTS 1 AND 43
06/18/2020 ENGR Engineering Final DROBERTS Approved Entered by DROBERT5 - THIS SITE IS COMPLETE EXCEPT FOR THE SIDEWALKS AT THE FOLLOWING LOTS 1 - 3, AND 43, THIS WORK IS BEING COMPLETED UNDER THE COMPLETION BOND.
10/03/2019 ENGR Engineering Final BBENEDON Partial Approval Entered by DMERANZ1 - Project appears to be 75% complete. There is construction in progress. Stormwater controls are still in place. Minor erosion issues need to be corrected. There are material stock piles blocking sidewalks and on Street. There is sediment within concrete drainage structures.
01/08/2018 ENGR Engineering Final RLEDONNE Continued Entered by RLEDONN1 - MET ON SITE WITH GRADING CONTRACTOR WALKED NORTH END OF SITE WENT OVER WORK TO COMPLET. WENT OVER AS-BUILTS CHANGE IN PIPING SIZE OF OUT LET PIPE FOR BASIN BY LOT #9 NOT ON AS-BUILTS. NEED TO COMPLET ALL LANDSCAPING SIDE WALKS ALL WORK ON AP PLANS AND CERT LETTER FROM ENGINEER OF RECORD. AND MONITORING REPORT FROM LANDSCAPE ARCHITECT FOR NPPO.
12/20/2017 ENGR Engineering Final RLEDONNE Not ready for Inspection Entered by RLEDONN1 - MEETING ON SITE NEXT WEEK .
11/01/2017 ENGR Engineering Final RLEDONNE Continued Entered by RLEDONN1 - WALKED SOUTH SIDE OF SITE UP TO LOT # 8 WITH MIKE FROM BORDERLAND CHECKING DRAINAGE AREAS AND PIPING/ RIP-RAP WENT OVER WORK TO COMPLET IN THAT AREA AND TO PROVIDE AS-BUILTS FOR ALL CHANGES TO AP PLANS AND CERT LETTER FROM ENGINEER OF RECORD.
10/27/2017 ENGR Engineering Final RLEDONNE Not ready for Inspection Entered by RLEDONN1 - WORKING ON REPAIRS TO SIDE WALKS AND RAMPS. IWALKED SOUTH SIDE OF SITE TO CHECK REPAIRS.
10/11/2017 ENGR Engineering Final RLEDONNE Not ready for Inspection Entered by RLEDONN1 - TALKED TO GRADING SUPER ABOUT SIDEWALKS THAT ARE OVER 2% CROSS SLOPES.