Permit: DP16-0044

Parcel: 13705494B


Addresses:

1050 W IRVINGTON RD


Inspection Status: Not Ready

Inspection History: PDSD Site/Engineering Division - Landscaping

Permit Number - DP16-0044

Inspection Description - PDSD Site/Engineering Division - Landscaping

Inspection Status - Not Ready

Date Description Inspector Results Comments
10/27/2022 PDSD Site/Engineering Division - Landscaping Not Ready
05/13/2021 PDSD Site/Engineering Division - Landscaping IVR USER Cancelled Entered by IVR USER - IVRS - AP canceled
07/16/2020 PDSD Site/Engineering Division - Landscaping BBENEDON Not ready for Inspection Entered by JSCHNEI2 - Not ready. Remove the nursery stakes from the trees.
05/21/2020 PDSD Site/Engineering Division - Landscaping BBENEDON Partial Approval Entered by RSALDAT1 - Partially approved. Lot 31
08/22/2019 PDSD Site/Engineering Division - Landscaping BBENEDON Partial Approval Entered by DMERANZ1 - Trees are being Installed at Rodeways in Southeast Portion of site. But have not been staled.
06/24/2019 PDSD Site/Engineering Division - Landscaping BBENEDON Not ready for Inspection Entered by DMERANZ1 - This is for an inspection of shell building 1080 W. Irvington. The landscaping has not yet been installed at this time. The parking lot has not yet been stripped and the accessible signs have not yet been installed. The trash enclosure footings and walls were built without inspection and will require a letter from the project engineer certify compliance with standard detail 6.01. The slab has not yet been poured please call for inspection when ready.
06/11/2019 PDSD Site/Engineering Division - Landscaping BBENEDON Not ready for Inspection Entered by CBELL1 - At 4830 S. Calle Santa Cruz, shell building. Complete and call for inspection of trash enclosure slab and bollard installation. Depressed landscape areas as required.
07/27/2018 PDSD Site/Engineering Division - Landscaping DROBERTS Approved Entered by DROBERT5 -
08/29/2019 PDSD Site/Engineering Division - Landscaping BBENEDON Continued Entered by DMERANZ1 - Many new trees have recently been installed, but have not yet been properly staked
07/15/2019 PDSD Site/Engineering Division - Landscaping BBENEDON Denied Entered by DMERANZ1 - Trees have not been properly staked and are falling over
07/01/2019 PDSD Site/Engineering Division - Landscaping BBENEDON Continued Entered by DMERANZ1 - The trees that have been planted are not properly stakedAnd some have started to fall over.
06/14/2019 PDSD Site/Engineering Division - Landscaping BBENEDON Continued Entered by DMERANZ1 - I communicated with Rob East of Bourne properties via email and phone conversation. I informed Rob that in the last area that I inspected, one shell building on the west end of the property. The landscaping/water harvesting areas did not appear to be depressed a minimum of 6 inches. I stated that The contractor is required to comply with the general notes on page 2 as well as the requirements on the water harvesting page, and that any changes to the approved drawings would require a city of Tucson approved plan revision. I told him that I would be happy to meet with him on site to look at his plans together and discuss any issues and remaining work for this project.
06/10/2019 PDSD Site/Engineering Division - Landscaping BBENEDON Partial Approval Entered by CBELL1 - Landscaper is installing trees on the side of property, however they are not properly staked. The nursery stakes are still in place.
05/01/2019 PDSD Site/Engineering Division - Landscaping BBENEDON Denied Entered by CBELL1 - Trees have not been properly staked
02/27/2019 PDSD Site/Engineering Division - Landscaping BBENEDON Continued Entered by CBELL1 - Many of the trees installed still have the nursery stake.
01/10/2019 PDSD Site/Engineering Division - Landscaping DROBERTS Continued Entered by DROBERT5 - LANDSCAPING WORK CONTINUES ON THIS SITE BUT DOES NOT APPEAR TO BE COMPLETED FULLY TO ALLOW FOR THE CLOSURE OF THIS ITEM.
11/30/2018 PDSD Site/Engineering Division - Landscaping BBENEDON Continued Entered by CBELL1 - Landscaping work is in progress along walkways and in parking Islands. Dirt in public walkways and parking areas needs to be removed for safety