| 04/11/2019 |
SITE - Stormwater Follow-up
|
DROBERTS |
Approved |
Entered by DROBERT5 - |
| 10/17/2017 |
SITE - Stormwater Follow-up
|
MRUSSO |
Continued |
Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME |
| 09/15/2017 |
SITE - Stormwater Follow-up
|
MRUSSO |
Continued |
Entered by DROBERT5 - NO STORM WATER CONCERNS AT THIS TIME |
| 05/02/2017 |
SITE - Stormwater Follow-up
|
MRUSSO |
Continued |
Entered by DROBERT5 - 1) RETAINING WALL NOT SHOWN ON THE SITE DEVELOPMENT PLAN, ONLY SHOWN ON THE ARCHITECTURAL PLANS.
2) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME |
| 01/20/2017 |
SITE - Stormwater Follow-up
|
MRUSSO |
Continued |
Entered by DROBERT5 - ENSURE YOU COMPLY WITH YOUR STORM WATER PERMIT AND SWPPP PLAN |
| 01/09/2017 |
SITE - Stormwater Follow-up
|
MRUSSO |
Continued |
Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME.
SWEEP UP TRACKED SOIL. |
| 12/22/2016 |
SITE - Stormwater Follow-up
|
MRUSSO |
Continued |
Entered by DROBERT5 - 1) RE-ESTABLISH SEDIMENT CONTROLS ALONG THE NORTH SIDE OF THE SITE
2) ENSURE STORM WATER SELF INSPECTIONS ARE PERFORMED AND DOCUMENTED
|
| 12/09/2016 |
SITE - Stormwater Follow-up
|
MRUSSO |
Continued |
Entered by DROBERT5 - NO STORM WATER CONCERNS AT THIS TIME |
| 12/07/2016 |
SITE - Stormwater Follow-up
|
MRUSSO |
Continued |
Entered by MRUSSO1 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME |
| 10/27/2016 |
SITE - Stormwater Follow-up
|
MRUSSO |
Continued |
Entered by MRUSSO1 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME |
| 10/12/2016 |
SITE - Stormwater Follow-up
|
MRUSSO |
Continued |
Entered by MRUSSO1 - 1) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
CONTINUE TO MAINTAIN SEDIMENT CONTROLS THROUGHOUT CONSTRUCTION
2) REPAIR OF SD PIPE ALONG NORTH SIDE.
3) CONTRACTOR INSTALLING RET. SYSTEM |
| 10/03/2016 |
SITE - Stormwater Follow-up
|
MRUSSO |
Continued |
Entered by MRUSSO1 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME |
| 09/15/2016 |
SITE - Stormwater Follow-up
|
MRUSSO |
Continued |
Entered by MRUSSO1 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME |
| 09/13/2016 |
SITE - Stormwater Follow-up
|
MRUSSO |
Continued |
Entered by MRUSSO1 - 1) CONTRACTOR INSTALL OF TWO 8" PVC ROOF DRAINS AND TIE IN TO MAIN 42" TRUNK LINE - OK TO COVER
2) ENSURE STORM WATER SELF INSPECTIONS ARE PERFORMED AND DOCUMENTED |
| 09/12/2016 |
SITE - Stormwater Follow-up
|
MRUSSO |
Continued |
Entered by MRUSSO1 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME |
| 08/30/2016 |
SITE - Stormwater Follow-up
|
MRUSSO |
Continued |
Entered by MRUSSO1 - 1) PROGRESS INSPECTION OF STORM WATER PIE INSTALL AND PREP FOR UNDERGROUND RETENTION BASIN INSTALL.
2) ENSURE STORM WATER SELF INSPECTIONS ARE PERFORMED AND DOCUMENTED. |
| 08/05/2016 |
SITE - Stormwater Follow-up
|
MRUSSO |
Continued |
Entered by MRUSSO1 - 1) ENSURE COMPLIANCE WITH YOUR SWPPP
2) MAINTAIN SEDIMENT CONTROLS THROUGHOUT CONSTRUCTION |
| 08/03/2016 |
SITE - Stormwater Follow-up
|
MRUSSO |
Continued |
Entered by MRUSSO1 - 1) CONTRACTOR INSTALLING 24" HDPE STORM PIPE FROM WEST TO EAST W/ 8" AND 12" LATERAL LINES - OK TO COVER
2) RE-ESTABLISH PERIMETER STORM WATER SEDIMENT CONTROLS ALONG NORTH SIDE OF SITE
3) ENSURE STORM WATER SELF INSPECTIONS ARE PERFORMED AND DOCUMENTED |
| 07/26/2016 |
SITE - Stormwater Follow-up
|
DROBERTS |
Continued |
Entered by DROBERT5 - NO CONCERNS AT THIS TIME, MIKE WILL RECHECK THIS SITE LATER THIS WEEK. |
| 08/01/2016 |
SITE - Stormwater Follow-up
|
MRUSSO |
Continued |
Entered by MRUSSO1 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME |
| 07/29/2016 |
SITE - Stormwater Follow-up
|
MRUSSO |
Continued |
Entered by MRUSSO1 - NO STORM WATER CONCERNS AT THIS TIME |
| 07/21/2016 |
SITE - Stormwater Follow-up
|
MRUSSO |
Continued |
Entered by MRUSSO1 - CONTRACTOR INSTALLING 48" HDPE STORM PIPE.
INSTALLED "T" FOR ROOF TIE-IN
NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME |
| 07/20/2016 |
SITE - Stormwater Follow-up
|
MRUSSO |
Continued |
Entered by MRUSSO1 - 1) CONTRCTOR INSTALLING SECTIONS OF 48" HDPE TRUNK LINE STORM PIPE, RUNNING SOUTH TO NORTH - OK TO COVER COMPLETED SECTIONS
2) ENSURE STORM WATER PLAN IS COMPLIED WITH THROUGHOUT CONSTRUCTION
NO OTHER SITE CONCERNS AT THIS TIME |
| 07/15/2016 |
SITE - Stormwater Follow-up
|
DROBERTS |
Continued |
Entered by DROBERT5 - THE SITE APPEARS TO BE OKAY AT THIS TIME, THERE APPEARS TO BE NO ISSUES AT THIS TIME. |
| 07/18/2016 |
SITE - Stormwater Follow-up
|
MRUSSO |
Continued |
Entered by MRUSSO1 - NO SIGNIFICANT STORMWATER CONCERNS AT THIS TIME |
| 07/13/2016 |
SITE - Stormwater Follow-up
|
MRUSSO |
Continued |
Entered by MRUSSO1 - 1) CONTRACTOR INSTALLED APPROXIMATELY 280' OF 36" HDPE STORM PIPE ALONG THE SOUTH PERIMETER OF THE SITE.
2) PIPE INSTALLED PER APPROVED PLANS - TRENCH BEDDED/PIPE BEDDED TO SPRING LINE - OK TO COVER
3) ENSURE TO CALL FOR INSPECTION FOR VERIFICATION OF LATERAL CONNECTIONS AND CATCH BASIN INSTALLS.
4) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME |