Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Passed
Inspection History: ENGR Grading Final
Permit Number - DP15-0196
Inspection Description - ENGR Grading Final
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/18/2018 | ENGR Grading Final | bbenedo1 | Approved | Entered by BBENEDO1 - |
09/21/2018 | ENGR Grading Final | bbenedo1 | Partial Approval | Entered by BBENEDO1 - Message provided previous day contains no contact information . Courtesey re inspection performed following day for Rick . 9181 grading rebar northwest corner / page number four Cypress. 9027 Rick Grant Construction 602-647-3449 Job trailer in alley behind building. |
09/20/2018 | ENGR Grading Final | BBENEDON | Not ready for Inspection | Entered by CMURPHY1 - could not locate contractor or work to be inspected. Please provide contact information for next inspection. |
12/18/2018 | ENGR Grading Final | bbenedo1 | Approved | Entered by BBENEDO1 - |
11/07/2018 | ENGR Grading Final | BBENEDON | Continued | Entered by CBELL1 - Contractor is installing sidewalk at water meter location. Contractor is painting the interior of the garage. Landscape areas are to be 6in below curb openings. Engineering inspector has no issues preventing a TCO |
09/20/2018 | ENGR Grading Final | BBENEDON | Continued | Entered by CMURPHY1 - forming curbs, backfilling water lines in Drive. |
08/03/2018 | ENGR Grading Final | DROBERTS | Continued | Entered by DROBERT5 - SITE VISIT ONLY, LOOKED OVER THE SITE AND HAVE ADVISED THEM OF WHERE WE WILL NEED TO BE CALLED IN FOR INSPECTIONS. |
05/21/2018 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - NO WORK OUT SIDE BUILDING AT THIS TIME. |
05/07/2018 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - ALL WORK AT THIS TIME IS INSIDE BUILDING. NO GRADING ACTIVITY. |
09/07/2017 | ENGR Grading Final | DROBERTS | Partial Approval | Entered by DROBERT5 - 8 INCH STORMDRAIN LINE APPROVED FOR BACKFILL |
12/18/2018 | ENGR Grading Final | BBENEDON | Approved | Entered by QJONES1 - APPROVED PER GRADING FINAL |
12/18/2018 | ENGR Grading Final | BBENEDON | Approved | Entered by QJONES1 - APPROVED PER GRADING FINAL |