Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Passed
Inspection History: ENGR Grading Final
Permit Number - DP15-0138
Inspection Description - ENGR Grading Final
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/04/2017 | ENGR Grading Final | RLEDONNE | Approved | Entered by RLEDONN1 - |
01/04/2017 | ENGR Grading Final | RLEDONNE | Approved | Entered by RLEDONN1 - |
12/23/2015 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - NO CONCERNS AT THIS TIME. |
04/25/2016 | ENGR Grading Final | DROBERTS | Continued | Entered by DROBERT5 - CREWS WORKING IN VARIOUS AREAS THROUGHOUT THIS SITE. |
01/04/2017 | ENGR Grading Final | RLEDONNE | Approved | Entered by RLEDONN1 - |
11/30/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - MET WITH GC ON SITE WENT OVER WORK TO COMPLET BEFORE GRADING FINAL. |
11/07/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - MET WITH GC ON SITE. |
10/13/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - TRASH ENCLOSUER REBAR TO THE SOUTH OF THEATER ONLY. |
06/17/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - WORKING ON GRADING PARKING AREA EAST AND NORTH EAST ON SITE . MET WITH GC. |
03/07/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - INSTALLING CURBING PER DETAIL 209 0N SITE. |
03/04/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - CATCH BASIN TO THE SOUTH OF DAVE AND BUSTERS. |
02/29/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - MET NEW GC FOR THE MOVIE THEATER WENT OVER SITE SEWER. |
02/22/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - PER HIGH LIGHTS ON AP PLANS. |
02/19/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - PER HIGH LIGHTS ON AP PLANS. |
02/18/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - STORM WATER PIPIING PER HIGH LIGHTS ON AP PLANS. |
02/17/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - PER HIGH LIGHTS ON AP PLANS. |
02/16/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - PER HIGH LIGHTS ON G-5 FOR CATCH BASIN . |
02/12/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by DROBERT5 - INSPECTION PER HIGH LIGHTS ON AP PLANS. |
02/11/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - INSPECTIONS PER HIGH LIGHTS ON AP PLANS. |
02/10/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - MANHOLES IN STORM WATER PIPING PER HIGH LIGHTS ON PAGE G-3. |
02/09/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - |
02/08/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - INSPECTION PER HIGH LIGHTS ON PAGES G-3&4&5. |
02/05/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - PER HIGHTS ON G-3 &G-6. |
02/04/2016 | ENGR Grading Final | RLEDONNE | Not ready for Inspection | Entered by RLEDONN1 - |
02/03/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - INSPECTIONS PER HIGH LIGHTS ON PADE C-3. |
02/01/2016 | ENGR Grading Final | RLEDONNE | Not ready for Inspection | Entered by RLEDONN1 - |
01/28/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - WORKING ON CATCH BASIN ON SOUTH EAST SIDE OF SITE. |
01/27/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - WORKING ON CATCH BASIN. |
01/26/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - STORM DRAIN PER HIGH LIGHTS ON PAGE G-6. |
01/22/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - INSPECTION PER HIGH LIGHTS ON PAGE G-6 |
01/20/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - WORKING ON STROM DRAIN PIPIING. |
01/19/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - INSTALLING STROM DRAIN PIPIING PER HIGH LIGHTS ON PAGE G-4 AND G-6. |
01/15/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - INSTALLING SADDLES FOR LATERALS PER HIGH LIGHTS ON AP PLANS FOR STROM DRAINS. |
01/14/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - INSPECTION PER HIGH LIGHTS ON PAGE G-6 FOR STORM WATER PIPING. |
01/13/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - INSPECTION PER HIGHLIGHTS ON PAGE6-4& 6-2 . |
01/12/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - INSTALLING STORM DRIAN PIPING PER HIGH LIGHTS ON AP PLANS. |
10/13/2016 | ENGR Grading Final | RLEDONNE | Approved | Entered by RLEDONN1 - TRASH ENCLOSUER REBAR SOUTH OF THEATER COMPLET. |
10/06/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - REBAR FOR SLAB FOR TRAS ENCLOSUER OK ONLY FOR DAVE AND BUSTERS. |
09/27/2016 | ENGR Grading Final | RLEDONNE | Not ready for Inspection | Entered by RLEDONN1 - INSTALL PER STANARD 6-01.0 6'' SLAB #4 REBAR AT 12'' OC BOTH WAYS FOR TRASH ENCLOSUER. |
09/12/2016 | ENGR Grading Final | DROBERTS | Continued | Entered by DROBERT5 - LOOKED AT THE TRASH ENCLOSURE FOR THE THEATRES, RON HAS LOOKED AT THE AREA FOR DAVE AND BUSTERS. |
09/09/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - TRASH ENCLOUSER FOR DAVE AND BUSTERS WALLS OK ONLY. |
09/09/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - INSTALL BOND BEAM PER AP PLANS. |
08/25/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - DAVE AND BUSTERS IN WALL REBAR FOR TRAS ENCLOUSER FRIST LIFT OK. |
08/24/2016 | ENGR Grading Final | RLEDONNE | Not ready for Inspection | Entered by RLEDONN1 - |
08/22/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - DAVE AND BUSTERS FOOTER FOR TRASH ENCLOUSER ONLY. AND FRIST GROUT FOR THEATER WALL FOR TRASH ENCLOUSER. |
08/17/2016 | ENGR Grading Final | RLEDONNE | Not ready for Inspection | Entered by RLEDONN1 - |
08/16/2016 | ENGR Grading Final | RLEDONNE | Not ready for Inspection | Entered by RLEDONN1 - |
08/10/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - REBAR MAT ON NORTH EAST SIDE OF AND TO THE NOTH OF THE THEATER. |
08/09/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - REBAR MAT ON NORTH EAST SIDE OF BUILDING FOR DRIVE. |
07/18/2016 | ENGR Grading Final | RLEDONN1 | Continued | Entered by RLEDONN1 - REBAR PARTIL ON NORTH SIDE OF MOVE THEATER. |
07/11/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - TRASH ENCLOUSER ON SOUTH WEST SIDE OF SITE FOOTER REBAR OK ONLY. |
04/06/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - FOOTER FOR SHADE STRUCTURE PER DTC-3 1. INSTALLED PER AP PLANS. |