Inspection Status: Passed
Inspection History: ENGR Engineering Final
| Date |
Description |
Inspector |
Results |
Comments |
| 04/11/2017 |
ENGR Engineering Final
|
DROBERTS |
Approved |
Entered by DROBERT5 - |
| 03/28/2017 |
ENGR Engineering Final
|
DROBERTS |
Denied |
Entered by DROBERT5 - 1) INSTALL ALL OF THE REQUIRED LANDSCAPING ITEMS THAT ARE HIGHLIGHTED ON SHEET #7 OF 7 PRIOR TO RESCHEDULING THIS FOR ANOTHER FINAL INSPECTION. 2)ALSO INSTALL THE REMAINING SIDEWALK THAT HAS NOT BEEN POURED ALONG THE WEST SIDE OF THE EXISTING BUILDING. 3) PROVIDE REVISED DRAWINGS FROM THE ENGINEER OF RECORD PLUS A CERTIFICATION LETTER FOR THIS SITE WHEN YOU SCHEDULE THE FINAL INSPECTIONS. |