Inspection Status: Passed
Inspection History: SITE - Stormwater Follow-up
| Date |
Description |
Inspector |
Results |
Comments |
| 12/01/2016 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Approved |
Entered by RLEDONN1 - |
| 02/29/2016 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by RLEDONN1 - REPAIRS NEEDED ON SOUTH WEST SIDE OF SITE. |
| 02/08/2016 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by RLEDONN1 - NO CONCERNS AT THIS TIME. |
| 01/15/2016 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by RLEDONN1 - NO CONCERNS AT THIS TIME. |
| 11/24/2015 |
SITE - Stormwater Follow-up
|
RLEDONN1 |
Continued |
Entered by RLEDONN1 - NO CONCERNS AT THIS TIME . |
| 10/13/2015 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by RLEDONN1 - NO CONCERNS AT THIS TIME. |
| 08/31/2015 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by RLEDONN1 - MET WITH GC REP TO MAKE REPAIRS TO NORTH SIDE OF SITE TO SWPPP CONTROLS. |
| 08/04/2015 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by RLEDONN1 - GOT WITH GC ABOUT REPAIRING SWPPP CONTROLS. |
| 07/15/2015 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by RLEDONN1 - NO CONCERNS AT THIS TIME. |
| 02/10/2015 |
SITE - Stormwater Follow-up
|
RLEDONN1 |
Continued |
Entered by RLEDONN1 - CALLED GC ABOUT SWPPP REPAIRS. |