Permit: DP13-0131

Parcel: 11310001A


Addresses:

1545 E COPPER ST


Inspection Status: Passed

Inspection History: SITE - Stormwater Follow-up

Permit Number - DP13-0131

Inspection Description - SITE - Stormwater Follow-up

Inspection Status - Passed

Date Description Inspector Results Comments
09/11/2014 SITE - Stormwater Follow-up MRUSSO Approved Entered by DROBERT5 -
08/14/2014 SITE - Stormwater Follow-up MRUSSO Continued Entered by DROBERT5 - NO SIGNIFICANT STORM WATER COCNERNS AT THIS TIME
06/17/2014 SITE - Stormwater Follow-up MRUSSO Continued Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
06/12/2014 SITE - Stormwater Follow-up MRUSSO Continued Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
06/04/2014 SITE - Stormwater Follow-up MRUSSO Continued Entered by DROBERT5 - NO SIGNIFICANT STORM WATER COCNERNS AT THIS TIME
05/07/2014 SITE - Stormwater Follow-up MRUSSO Continued Entered by DROBERT5 - 1) THE CONTRACTOR IS WORKING ON CONSTRUCTION OF THE BLDG, MINIMAL SITE WORK AT THIS TIME. 2) SITE IS STILL UNDER A STORM WATER PERMIT, AND MUST COMPLY UNTIL THE SITE IS 100% STABILIZED 3) ENSURE EXISTING CATCH BASINS ARE COVERED AND SOIL IS KEPT OUT OF STORM SYSTEM
04/22/2014 SITE - Stormwater Follow-up MRUSSO Continued Entered by DROBERT5 - 1) CONTRACTOR WORKING ON BLDG CONSTRUCTION 2) UNDERGROUND STORM DRAINAGE SYSTEM INSTALLED, CONTRACTOR COVERED OR PROTECTED ALL CATCH BASINS. 3) ENSURE PERIMETER SEDIMENT CONTROLS REMAIN IN PLACE UNTIL THE SITE IS 100% STABILIZED
02/28/2014 SITE - Stormwater Follow-up MRUSSO Continued Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
02/19/2014 SITE - Stormwater Follow-up MRUSSO Continued Entered by DROBERT5 - ENSURE TO INSTALL SEDIEMNT CONTROLS AROUND NEW CATCH BASINS TO PROTECT THE STORM SYSTEM.
01/28/2014 SITE - Stormwater Follow-up MRUSSO Continued Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
01/27/2014 SITE - Stormwater Follow-up MRUSSO Continued Entered by DROBERT5 - 1) INSPECTED BUBBLER BOX AT THE END OF THE STORM WATER DRAINAGE RUN. ENSURE PIPE IS INSTALLED PER APPROVED PLAN. PICTURES TAKEN 2) WILL RE-INSPECT AND DOCUMENT PIPE TO BOX CONNECTION MONDAY 1/27/14 3) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME.
01/17/2014 SITE - Stormwater Follow-up MRUSSO Continued Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
01/13/2014 SITE - Stormwater Follow-up DROBERTS Continued Entered by DROBERT5 - NO CONCERNS AT THIS TIME.
01/14/2014 SITE - Stormwater Follow-up MRUSSO Continued Entered by DROBERT5 - 1) CONTRACTOR INSTALLING 24" CMP ALONG SOUTH SIDE OF SITE. PIPE HAS LATERAL CONNECTIONS FROM TWO CATCH BASINS AND MULTIPLE ROOF DRAIN TIE-INS. 2) SOME DIRECTIONAL CHANGES HAVE BEEN MADE TO THE LATERALS AND THERE IS NO DETAIL SHOWING THE CONNECTION OF THE MANY ROOF DRAINS TO THE MAIN BRANCH LINE. 3) ALL CHANGES FORM THE ORIGINAL APPROVED SITE/GRADING PLAN NEED TO BE SHOWN ON AN AS-BUILT DRAWING. 4) PROVIDE APPROVAL FROM THE ENGINEER OF RECORD AND THE ENG REVIEWER FOR ROOF DRAIN TO STORM PIPE CONNECTIONS (RUBBER STOPPER USED AROUND PIPE, HOLE CUT INTO MAIN LINE AND ROOF DRAIN GROUTED IN PLACE). 5) NO STORM WATER CONCERNS AT THIS TIME
12/31/2013 SITE - Stormwater Follow-up MRUSSO Continued Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
12/24/2013 SITE - Stormwater Follow-up MRUSSO Continued Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
12/23/2013 SITE - Stormwater Follow-up MRUSSO Continued Entered by DROBERT5 - UNDERGROUND STORM WATER CANCELLED DUE TO RAIN NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
12/13/2013 SITE - Stormwater Follow-up MRUSSO Continued Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
12/10/2013 SITE - Stormwater Follow-up MRUSSO Continued Entered by DROBERT5 - 1) CONTRACTOR INSTALLED APRROX 180' OF 12 AND 18" PVC STORM DRAIN PIPIE AND TWO PRE-CAST CATCH BASINS. 2) THE PIPE TRENCH WAS COMPACTED AND SHADED TO THE SPRING LINE 3) PIPE WAS GRADED TO DRAIN PER THE APPROVED PLANS 4) CATCH BASINS WERE PRE-CAST AND SET IN PLACE, PIPE WAS GROUTED IN - PICTURES WERE TAKEN 5) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME