Inspection Status: Passed
Inspection History: ENGR Engineering Final
| Date |
Description |
Inspector |
Results |
Comments |
| 06/26/2015 |
ENGR Engineering Final
|
MRUSSO1 |
Approved |
Entered by DROBERT5 - |
| 04/29/2015 |
ENGR Engineering Final
|
MRUSSO |
Continued |
Entered by DROBERT5 - NO CHANGES WITH PHASE I COMPLETION |
| 04/01/2015 |
ENGR Engineering Final
|
MRUSSO |
Continued |
Entered by DROBERT5 - PRIOR TO FINAL APPROVAL COMPLETE ALL CONSTRUCTION PER THE APPROVED PLANS |
| 01/30/2015 |
ENGR Engineering Final
|
MRUSSO |
Prior to Final Inspectn |
Entered by DROBERT5 - PRIOR TO FINAL:
1) COMPLETE SITE GRADING AND LANDSCAPING PER APPROVED PLANS
2) PROVIDE A CERT STATEMENT FROM THE ENGINEER OF RECORD AND LANDSCAPE ARCHITECT STATING THAT SITE/GRADING/ AND LANDSCAPING WAS COMPLETED PER PLAN
3) PROVIDE AND AS-BUILT TO THE CITY OF TUCSON
4) FILE A "NOT" WITH ADEQ.
5) ENSURE ELEVATION CERTIFICATION HAS BEEN SUBMITTED.
PRIOR TO APPROVAL FOR ENG, LANDSCAPING, SIGN, AND NPPO ON YOUR BLDG PERMIT: (TEMP C OF O)
1) SEPARATE THE REMAINING CONSTRUCTION FROM PUBLIC ACCESS
2) PROVIDE SAFE PARKING, ACCESS, TRASH SERVICE, LANDSCAPING AND ALL OTHER SERVICES NEEDED TO OCCUPY THE NEW BLDG. |
| 01/07/2015 |
ENGR Engineering Final
|
MRUSSO |
Continued |
Entered by DROBERT5 - 1) PRIOR TO FINAL PROVIDE A CERT STATEMENT FROM THE ENG OF RECORD
2) PROVIDE AN AS-BUILT DRAWING TO THE CITY OF TUCSON
3) ENSURE ALL SITE/GRADING WAS COMPLETED PER APPROVED PLAN |
| 04/04/2013 |
ENGR Engineering Final
|
eleibol1 |
Prior to Final Inspectn |
Entered by ELEIBOL1 - Elevation Certificates will be required for each structure for post construction. |