Inspection Status: Passed

Inspection History: SITE - Stormwater Setup and Controls

Date Description Inspector Results Comments
04/25/2017 SITE - Stormwater Setup and Controls DROBERTS Approved Entered by DROBERT5 -
03/01/2013 SITE - Stormwater Setup and Controls MRUSSO Continued Entered by DROBERT5 - 1) RE-ESTABLISH YOUR ROCK ENTRANCE'S/EXIT'S MAY NEED TO EXPAND THIER SIZE TO ACCOMIDATE THE AMOUNT OF CONSTRUCTION TRAFFIC. 2) CONTINUE TO SWEEP UP TRACKED SOIL OFF OF PUBLIC ROADWAYS ROUTINELY - MORE OFTEN AS NEEDED 3) A "V" DITCH/BIRM HAS BEEN INSTALLED AROUND THE PERIMETER OF THE CONSTRUCTION SITE. HOWEVER SECTIONS OF THE DITCH NEED TO BE RE-COMPACTED AND/OR REPAIRED. 4) INSTALL AND USE A CONCRETE/MATERIALS WASH OUT ON SITE. 5) ENSURE YOU PERFORM AND DOCUMENT STORM WATER SELF INSPECTIONS PER YOU SWPPP 6) POST A COPY OF YOUR NOI AT THE ENTRANCE TO THE SITE.