Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Passed
Inspection History: ENGR Grading Final
Permit Number - DP12-0192
Inspection Description - ENGR Grading Final
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/19/2013 | ENGR Grading Final | DROBERTS | Approved | Entered by DROBERT5 - |
03/19/2013 | ENGR Grading Final | DROBERTS | Approved | Entered by DROBERT5 - |
03/19/2013 | ENGR Grading Final | DROBERTS | Approved | Entered by DROBERT5 - |
02/27/2013 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - PROVIDE LETTER FOR CHANGE TO KEY NOTE #1 FOR LANDSCAPE.FROM WAYEN SWAN. |
02/25/2013 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - WALKED SITE WITH G.C AND ENGINEER. |
02/11/2013 | ENGR Grading Final | DROBERTS | Continued | Entered by DROBERT5 - MET WITH THE CONTRACTOR AND DISCUSSED WHAT IS HAPPENING WITH THIS SITE AT THIS TIME. THEY HAVE GRUBBED THE SITE AND HAVE PLACED ALL OF THE NPPO PLANTS INTO A SMALL NURSARY LOCATED IN THE NORTH EAST CORNER OF THE SITE. THE NPPO AND LANDSCAPING PLANS HAVE NOT BEEN APPROVED AT THIS TIME SO THE CREWS ARE WAITING FOR ADDITIONAL INSTRUCTIONS OF WHAT CAN BE DONE BEFORE THESE PLANS ARE APPROVED. THEY ARE PLANNING ON WORKING ON THE CONSTRUCTION OF THE BASIN AREA IN THE NEXT FEW DAYS, ANTICIPATING THAT ALL THE PLANS WILL BE APPROVED AT THAT TIME. |
03/19/2013 | ENGR Grading Final | DROBERTS | Approved | Entered by KMEDINA1 - |
02/11/2013 | ENGR Grading Final | DROBERTS | Not Applicable | Entered by DROBERT5 - NOT APPLICABLE AT THIS TIME CREWS HAVE BEEN WORKING ON THIS PROJECT. |