Inspection Status: Passed
Inspection History: ENGR Engineering Final
| Date |
Description |
Inspector |
Results |
Comments |
| 05/20/2013 |
ENGR Engineering Final
|
MRUSSO |
Approved |
Entered by DROBERT5 - |
| 03/14/2013 |
ENGR Engineering Final
|
MRUSSO |
Partial Approval |
Entered by DROBERT5 - 1) LANDSCAPE FINAL APPROVED.
2) NEED TO REMOVE ALL TEMP SEDIMENT CONTROLS
3) NEED TO PROVIDE A CERT STATEMENT FROM THE ENG OF RECORD STATING THAT THE RET/DET BASIN WAS CONSTRUCTED PER THE APPROVED PLAN |
| 01/18/2013 |
ENGR Engineering Final
|
MRUSSO |
Continued |
Entered by DROBERT5 - MET WITH SUPERINTENDENT
1) DISTURBED AREAS NEED TO BE HYDROSEEDED PER PLAN
2) NEED ENG OF RECORDS CERT STATEMENT
3) NEED AS-BUILT
4) CONTRACTOR NEEDS TO COMPLETE LANDSCAPING
5) NEED TO REMOVE TEMP SEDIMENT CONTROLS |
| 01/16/2013 |
ENGR Engineering Final
|
MRUSSO |
Partial Approval |
Entered by DROBERT5 - 1) REMOVE TEMPORARY SEDIMENT CONTROLS
2) ALL DISTURBED AREAS NEED TO BE HYDROSEEDED, PER PLAN
3) GIVE JUSTIFICATION FOR THE CMU TO CHAIN LINK FENCE CHANGE
4) COMPLETE LANDSCAPING
5) PROVIDE BASIN CERT FROM THE ENG OF RECORD |
| 01/14/2013 |
ENGR Engineering Final
|
MRUSSO |
Partial Approval |
Entered by DROBERT5 - SITE MOSTLY COMPLETE, CONTRACTOR WORKING ON RET/DET BASINS ALONG NORTH SIDE |
| 11/26/2012 |
ENGR Engineering Final
|
MRUSSO |
Continued |
Entered by DROBERT5 - MAJORITY OF SITE WORK DONE, HOWEVER, RET/DET BASIN HAS NOT BEEN COMPLETED PER APPROVED PLAN.
CALL FOR FINAL APPROVAL WHEN COMPLETE. |
| 10/19/2012 |
ENGR Engineering Final
|
MRUSSO |
Partial Approval |
Entered by DROBERT5 - 1) THE MAJORITY OF THE SITE IS COMPLETE
2) SOME WORK BEING DONE ON RET/DET BASINS, ENSURE ROCK RIP RAP AND TOE DOWNS ARE INSTALLED PROPERLY.
3) SITE IS MOSTLY STABILIZED. ENSURE (NOT) IS FILED WITH THE STATE OF AZ
4) PROVIDE A CERT STATEMENT FROM YOUR ENG OF RECORD
5) SUBMIT AS-BUILT DRAWING AT FINAL
|