Inspection History Details
Inspection Status: Passed
Inspection History: SITE - Stormwater Follow-up
Permit Number - DP12-0072
Inspection Description - SITE - Stormwater Follow-up
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/19/2012 | SITE - Stormwater Follow-up | MRUSSO | Approved | Entered by DROBERT5 - 1) THE MAJORITY OF PAVING IS COMPLETE 2) SOME LANDSCAPING COMPLETE 3) ALL SIDEWALKS IN 4) ENSURE APPROVED PLAN REFLECTS CHANGES MADE TO ORIGINAL DRAWING 5) PROVIDE CERT FROM ENG OF RECORD 6) FILE NOT WITH THE STATE OF AZ |
10/09/2012 | SITE - Stormwater Follow-up | MRUSSO | Continued | Entered by DROBERT5 - 1) SEDIMENT CONTROLS ARE IN PLACE. 2) ENSURE SEDIMENT CONTROLS ARE MAINTAINED THROUGHOUT CONSTRUCTION. 3) INSTALL A CONCRETE WASH OUT AS SOON AS POSSIBLE. 4) TRACKING OF SOIL ON ADJACENT ROADWAY IS A CONCERN. ADD SILT SOCK ON THE UPSTEAM SIDE OF THE EXISTING CATCH BASIN IN THE CURB LINE. SWEEP UP SOIL ON A ROUTINE BASIS. RE-ESTABLISH YOUR STABILIZED CONSTRUCTION ENTRANCE. CALL FOR RE-INSPECTION WHEN COMPLETED. |
09/19/2012 | SITE - Stormwater Follow-up | MRUSSO | Continued | Entered by DROBERT5 - 1) ENSURE TRACKED SOIL IS SWEPT UP OFF ADJACENT ROADWAY. 2) MAKE SURE SIGNIFICANT CHANGES TO THE ORIGINAL GRADING/SITE PLANARE DOCUMENTED AND APPROVED. 3) MAINTAIN SEDIMENTCONTROLS (SILT FENCE) AS LONG AS ITS IN PLACE - CAN REMOVE WHEN PAVING IS COMPLETE. 4) NO OTHER CONCERNS AT THIS TIME. |
09/05/2012 | SITE - Stormwater Follow-up | MRUSSO | Continued | Entered by DROBERT5 - NO CHANGES AND OR CONCERNS AT THIS |
08/22/2012 | SITE - Stormwater Follow-up | MRUSSO | Continued | Entered by DROBERT5 - 1) TRACKING ALONG ADJACENT STREET HAS BEEN SWEPT AND SEDIMENT CONTROLS HAVE BEEN PLACED IN FRONT OF THE EXISTING CATCH BASIN. 2) SITE HAS BEEN ROUGH GRADED, PAVING WILL BEGIN SOON. NO OTHER SIGNIFICANT CONCERNS AT THIS TIME. |
08/16/2012 | SITE - Stormwater Follow-up | MRUSSO | Continued | Entered by DROBERT5 - 1) SEDIMENT CONTROLS ARE IN PLACE. 2) ENSURE SEDIMENT CONTROLS ARE MAINTAINED THROUGHOUT CONSTRUCTION. 3) INSTALL A CONCRETE WASH OUT AS SOON AS POSSIBLE. 4) TRACKING OF SOIL ON ADJACENT ROADWAY IS A CONCERN. ADD SILT SOCK ON THE UPSTEAM SIDE OF THE EXISTING CATCH BASIN IN THE CURB LINE. SWEEP UP SOIL ON A ROUTINE BASIS. RE-ESTABLISH YOUR STABILIZED CONSTRUCTION ENTRANCE. CALL FOR RE-INSPECTION WHEN COMPLETED. |