Inspection Status: Passed
Inspection History: PDSD Engineering Division Pre-Construction SITE
| Date |
Description |
Inspector |
Results |
Comments |
| 06/07/2012 |
PDSD Engineering Division Pre-Construction SITE |
MRUSSO |
Approved |
Entered by DROBERT5 - LECHNER CONSTRUCTION
PETER STANEK 850-8912
1) ENGINEERING PRE-CON MEETING ACCOMPLISHED. MET WITH SUPERINTENDENT ON SITE DISCUSSED SITE WORK AND STORM WATER REQUIREMENTS.
2) SITE IS LESS THAN 1 ACRE, NO SWPP REQUIRED HOWEVER THE CONTRACTOR IS STILL REQUIRED TO KEEP SOIL ON SITE DURING CONSTRUCTION, WHILE WORKING IN THE CITY LIMITS.
3) THREE MESQUITE TREES WERE PRESERVED IN PLACE IN ACCORDANCE WITH THIER NPPO/LANDSCAPING PLAN.
4) ENSURE DISTURBED SOIL IS NOT TRACKED ONTO PRINCE ROAD.
5) ALL WASTE MATERIALS USED ON SITE MUST BE DISPOSED OF PROPERLY.
6) ENSURE SITE WORK IS COMPLETED PER YOUR APPROVED GRADING PLAN/LANDSCAPE PLAN. ANY CHANGES MUST BE APPROVED AND SHOWN ON A REVISED PLAN.
7) CALL FOR INSPECTION FOR ANY CONCERNS AND/OR CHANGES MADE |