Inspection Status: Passed
Inspection History: COT - ENFC - Code Enforcement - Follow Up
| Date |
Description |
Inspector |
Results |
Comments |
| 02/01/2026 |
COT - ENFC - Code Enforcement - Follow Up |
|
Passed |
Permit TC-RES-0825-04139 is in a complete status. |
| 08/27/2025 |
COT - ENFC - Code Enforcement - Follow Up |
|
In Violation |
On 8/21/25 permit TC-RES-0825-04139 PDSD Application Completeness Express permit was reviewed. There are other steps in the permit process pending. Will follow up in 30 days. |
| 10/07/2025 |
COT - ENFC - Code Enforcement - Follow Up |
|
In Violation |
Homeowner is still in inspections stage of the permit process. BULD - Electrical Clearance (Inspection) was completed today. TC-RES-0825-04139. Will continue to follow up every 2 weeks until permit is in complete status. |
| 10/30/2025 |
COT - ENFC - Code Enforcement - Follow Up |
|
In Violation |
Permit is still in review with PDSD but in the final stages of the inspection process. Will f/u in 30 days. |
| 12/11/2025 |
COT - ENFC - Code Enforcement - Follow Up |
|
In Violation |
COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Partial Pass status for permit: TC-RES-0825-04139. will f/u in 30 days |