Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Case: CE-VIO0725-03161

Parcel: 106063300


Addresses:

3660 N NUFER PL

Inspection Status: Passed

Inspection History: COT - ENFC - Code Enforcement - Follow Up

Date Description Inspector Results Comments
02/01/2026 COT - ENFC - Code Enforcement - Follow Up Passed Permit TC-RES-0825-04139 is in a complete status.
08/27/2025 COT - ENFC - Code Enforcement - Follow Up In Violation On 8/21/25 permit TC-RES-0825-04139 PDSD Application Completeness Express permit was reviewed. There are other steps in the permit process pending. Will follow up in 30 days.
10/07/2025 COT - ENFC - Code Enforcement - Follow Up In Violation Homeowner is still in inspections stage of the permit process. BULD - Electrical Clearance (Inspection) was completed today. TC-RES-0825-04139. Will continue to follow up every 2 weeks until permit is in complete status.
10/30/2025 COT - ENFC - Code Enforcement - Follow Up In Violation Permit is still in review with PDSD but in the final stages of the inspection process. Will f/u in 30 days.
12/11/2025 COT - ENFC - Code Enforcement - Follow Up In Violation COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Partial Pass status for permit: TC-RES-0825-04139. will f/u in 30 days