Case: T16DV03108
Case Details
Entered Date:
05/25/2016
Applicant:
PRIME TANQUE VERDE LLC MAIN FLOOR
Description:
COMMERCIAL FIRE
Outstanding Inspections
Case Number: T16DV03108
Case Status: COMPLIAN
Case Description: FIRE AT COMMERCIAL BUILDING
Total Outstanding Inspections - 1
| End Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/16/2016 | NPO - WORK WITHOUT PERMIT | VIDAL | Item closed |
Completed Inspections
Case Status: COMPLIAN
Case Number: T16DV03108
Case Description: FIRE AT COMMERCIAL BUILDING
Total Completed Inspections - 2
| End Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/25/2016 | INSP - INITIAL CODE ENFORCMENT | NAVARRO | Approved | vISITED SITE, MET tfd ON SITE, INSPECTED, FOUND AS FOLLOWS: 1: FIRE ON PORCH 2)FLOOR JOISTS WERE DAMAGED 3) STUCCO DAMAGED 4) SHEETROCK DAMAGED INSIDE BUILDING 5) MET MANAGER ON SITE 6) WROTE NOTICE OF VIOLATION ON SITE 7) HAD MANAGER SIGN 8) GAVE COPY OF NOTICE OF VIOLATION 9) EXPLAINED PROCESS 10) POWER WAS TURNED OFF AT BREAKER, EXPLAINED TO MANAGER HIS RESPONSEABILITIE TO TURN POWER ON AND SECURE UNIT 11) NO ELECTRICAL,HVAC,WATER OR GAS DAMAGE- ALL UTILITIES REMAIN ON. 12) FOLLOW UP IN SIXTY DAYS |
| 08/16/2016 | INSP - FOLLOW UP CODE ENFORCE | VIDAL | Approved | The fire was on the bottom unit and was started with a grill fire on the porch. The upper deck was damaged with the stucco on the bottom. The sliding glass door and window to the living room area by the front door was broken during the fire. The sliding glass door has been replaced with new, the upper deck has all been replaced with new and like for like. The damage stucco has been removed and the foam is being installed to do the stucco repairs. Some drywall has been removed in the living room area where the fire fighters made holes in the wall to check for fire. Did not find a permit and met with the manager and she called the contractor to talk to. Did advise that a permit is required and was written on the Notice of Violation and the manager made a copy and sent it to the contractor. Will go back to the office to check with pictures if the permit is required or not. Will call the contractor back. Will check in 10 days. RV. |
Completed Activity Special Conditions
Case Description - FIRE AT COMMERCIAL BUILDING
Case Number - T16DV03108
Case Status: COMPLIAN
Total Completed Case Activity Conditions: 7
| Date | Name |
| 08/16/2016 | CONTACTED BY PHONE |
| 05/26/2016 | CONTACTED IN PERSON |
| 05/26/2016 | CONTACTED BY MAILING |
| 08/16/2016 | CONTACTED BY EMAIL |
| 05/26/2016 | NOTICE OF VIOLATION ISSUED |
| 11/14/2016 | VIOLATION CLOSED |
| 08/16/2016 | RESEARCH |