PDSD REFERRAL - Friedman Recycling has a damaged column. There is a structural column which is nearly 2' out of plumb after having been hit by equipment. ***VIEW EMAIL REFERRAL IN SIRE***
Case Violations
Case Number: T12DV00368
Case Status: COMPLIAN
Case Description: ENVIRONMENTAL
Total Violations: 2
Violation Date | Code Statue |
---|---|
01/25/2012 | T.C. Ch. 16, Sec. 16-11(f)(1) Every wall or vertical support must be sufficient to carry imposed loads safely, and must not lean, buckle, or split due to defect or lack of maintenance. |
01/25/2012 | T.C. Ch. 16, Sec. 16-11(f)(2) Every ceiling, roof, and ceiling and roof support must be sufficient to carry imposed loads safely, and must not buckle, sag or split due to defective material or deterioration. |
Outstanding Inspections
Case Number: T12DV00368
Case Status: COMPLIAN
Case Description: ENVIRONMENTAL
Total Outstanding Inspections - 2
End Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/03/2012 | NPO - EXT. HAZ/ATTRACT NUISANC | ESTEVENS | Item closed | |
10/03/2012 | NPO - EXT. BUILDING MAINTENANC | ESTEVENS | Item closed |
Completed Inspections
Case Status: COMPLIAN
Case Number: T12DV00368
Case Description: ENVIRONMENTAL
Total Completed Inspections - 2
End Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/23/2012 | INSP - INITIAL CODE ENFORCMENT | ESTEVENS | Approved | At site with Armando Q. with DSD. After assessing damage to I-beam structure, we determined that the structure should be examined by a structural engineer. I spoke to Jose Penna, plant manager. I explained the issues and concerns of the city and informed him about getting a structural engineer to examine the bent framework. Explianed the NOV and re-inspections fees. F/U 30 days. |
10/03/2012 | INSP - FOLLOW UP CODE ENFORCE | ESTEVENS | Approved | At site, walked warehouse, I-beams and supports have been replaced, like for like, issue abated, close case. |
Completed Activity Special Conditions
Case Description - ENVIRONMENTAL
Case Number - T12DV00368
Case Status: COMPLIAN
Total Completed Case Activity Conditions: 5
Date | Name |
02/23/2012 | CONTACTED BY PHONE |
01/27/2012 | CONTACTED BY MAILING |
01/19/2012 | CONTACTED BY EMAIL |
01/27/2012 | NOTICE OF VIOLATION ISSUED |
10/04/2012 | VIOLATION CLOSED |