Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Address Search: 1200 E BILBY RD
Search
Annexations & Original City Zoning (OCZ)
Address: 1200 E BILBY RD
Date - 11/13/2024 5:48 a.m.
Total Number Of Annexations & Original City Zoning (1)
Special Development Requests & Requirements
Address: 1200 E BILBY RD
Date - 11/13/2024 5:48 a.m.
Total Number Of Special Development Permits - (1)
Activity Number | Status | Apply Date | Expired Date | Unit | Type | Description |
---|---|---|---|---|---|---|
H000005422 | CLOSED | 09/05/2013 | N/A | Historical Information | RECORD TO SHOW BILLBOARD AZ488/CLEAR CHANNEL #301 REMOVED DUE TO STORM DAMAGE |
Permits
Address: 1200 E BILBY RD
Date - 11/13/2024 5:48 a.m.
Total Number Of Permits - (51)
Permit | Status | Apply Date | Expired Date | Unit | Type | Description |
---|---|---|---|---|---|---|
TC-COM-1123-02655 | Issued | 11/14/2023 | 01/14/2025 | Commercial Building | south service upgrades including 3 new 200 amp boxes and new gutter with new wire: REV 1: Like-for-like replacement of equipment and conductors. No service upgrade. | |
T19MH00107 | Issued | 08/22/2019 | 02/18/2020 | Residential Building - One or Two Family | MH REPLACEMENT | |
TC-COM-0723-01809 | Fees Paid | 07/25/2023 | 01/21/2024 | Commercial Building | Like for like wire replacement. wire replacement inside the gutter. This permit is not related to TC-COM-0423-01160. We have two different tep meters that are getting worked on at the same time | |
TC-COM-0723-01740 | Void | 07/18/2023 | 01/14/2024 | Commercial Building | Void - Duplicate/Same scope of work as existing application permit number TC-COM-0423-01160. Please submit revision under existing permit or withdraw existing permit before moving forward with a new application.replace wires inside the gutter box. no boxes being repalced | |
TR-ROW-0623-00898 | Complete | 06/22/2023 | 08/27/2023 | Right-of-Way (ROW) | Air-vacuum excavation of 30 utility potholes for the design phase of Tucson DOT Prop 411 Neighborhood St. Improvements Bilby Rd Modernization Project | |
TR-ROW-0623-00898 | Complete | 06/22/2023 | 08/27/2023 | UNIT 13 | Right-of-Way (ROW) | Air-vacuum excavation of 30 utility potholes for the design phase of Tucson DOT Prop 411 Neighborhood St. Improvements Bilby Rd Modernization Project |
TR-ROW-0623-00898 | Complete | 06/22/2023 | 08/27/2023 | UNIT 18 | Right-of-Way (ROW) | Air-vacuum excavation of 30 utility potholes for the design phase of Tucson DOT Prop 411 Neighborhood St. Improvements Bilby Rd Modernization Project |
TR-ROW-0623-00898 | Complete | 06/22/2023 | 08/27/2023 | UNIT 2 | Right-of-Way (ROW) | Air-vacuum excavation of 30 utility potholes for the design phase of Tucson DOT Prop 411 Neighborhood St. Improvements Bilby Rd Modernization Project |
TR-ROW-0623-00898 | Complete | 06/22/2023 | 08/27/2023 | UNIT 21 | Right-of-Way (ROW) | Air-vacuum excavation of 30 utility potholes for the design phase of Tucson DOT Prop 411 Neighborhood St. Improvements Bilby Rd Modernization Project |
TR-ROW-0623-00898 | Complete | 06/22/2023 | 08/27/2023 | UNIT 24 | Right-of-Way (ROW) | Air-vacuum excavation of 30 utility potholes for the design phase of Tucson DOT Prop 411 Neighborhood St. Improvements Bilby Rd Modernization Project |
TR-ROW-0623-00898 | Complete | 06/22/2023 | 08/27/2023 | UNIT 26 | Right-of-Way (ROW) | Air-vacuum excavation of 30 utility potholes for the design phase of Tucson DOT Prop 411 Neighborhood St. Improvements Bilby Rd Modernization Project |
TR-ROW-0623-00898 | Complete | 06/22/2023 | 08/27/2023 | UNIT 29 | Right-of-Way (ROW) | Air-vacuum excavation of 30 utility potholes for the design phase of Tucson DOT Prop 411 Neighborhood St. Improvements Bilby Rd Modernization Project |
TR-ROW-0623-00898 | Complete | 06/22/2023 | 08/27/2023 | UNIT 31 | Right-of-Way (ROW) | Air-vacuum excavation of 30 utility potholes for the design phase of Tucson DOT Prop 411 Neighborhood St. Improvements Bilby Rd Modernization Project |
TR-ROW-0623-00898 | Complete | 06/22/2023 | 08/27/2023 | UNIT 34 | Right-of-Way (ROW) | Air-vacuum excavation of 30 utility potholes for the design phase of Tucson DOT Prop 411 Neighborhood St. Improvements Bilby Rd Modernization Project |
TR-ROW-0623-00898 | Complete | 06/22/2023 | 08/27/2023 | UNIT 36 | Right-of-Way (ROW) | Air-vacuum excavation of 30 utility potholes for the design phase of Tucson DOT Prop 411 Neighborhood St. Improvements Bilby Rd Modernization Project |
TR-ROW-0623-00898 | Complete | 06/22/2023 | 08/27/2023 | UNIT 38 | Right-of-Way (ROW) | Air-vacuum excavation of 30 utility potholes for the design phase of Tucson DOT Prop 411 Neighborhood St. Improvements Bilby Rd Modernization Project |
TR-ROW-0623-00898 | Complete | 06/22/2023 | 08/27/2023 | UNIT 39 | Right-of-Way (ROW) | Air-vacuum excavation of 30 utility potholes for the design phase of Tucson DOT Prop 411 Neighborhood St. Improvements Bilby Rd Modernization Project |
TR-ROW-0623-00898 | Complete | 06/22/2023 | 08/27/2023 | UNIT 40 | Right-of-Way (ROW) | Air-vacuum excavation of 30 utility potholes for the design phase of Tucson DOT Prop 411 Neighborhood St. Improvements Bilby Rd Modernization Project |
TR-ROW-0623-00898 | Complete | 06/22/2023 | 08/27/2023 | UNIT 41 | Right-of-Way (ROW) | Air-vacuum excavation of 30 utility potholes for the design phase of Tucson DOT Prop 411 Neighborhood St. Improvements Bilby Rd Modernization Project |
TR-ROW-0623-00898 | Complete | 06/22/2023 | 08/27/2023 | UNIT 42 | Right-of-Way (ROW) | Air-vacuum excavation of 30 utility potholes for the design phase of Tucson DOT Prop 411 Neighborhood St. Improvements Bilby Rd Modernization Project |
TR-ROW-0623-00898 | Complete | 06/22/2023 | 08/27/2023 | UNIT 43 | Right-of-Way (ROW) | Air-vacuum excavation of 30 utility potholes for the design phase of Tucson DOT Prop 411 Neighborhood St. Improvements Bilby Rd Modernization Project |
TR-ROW-0623-00898 | Complete | 06/22/2023 | 08/27/2023 | UNIT 44 | Right-of-Way (ROW) | Air-vacuum excavation of 30 utility potholes for the design phase of Tucson DOT Prop 411 Neighborhood St. Improvements Bilby Rd Modernization Project |
TR-ROW-0623-00898 | Complete | 06/22/2023 | 08/27/2023 | UNIT 46 | Right-of-Way (ROW) | Air-vacuum excavation of 30 utility potholes for the design phase of Tucson DOT Prop 411 Neighborhood St. Improvements Bilby Rd Modernization Project |
TR-ROW-0623-00898 | Complete | 06/22/2023 | 08/27/2023 | UNIT 48 | Right-of-Way (ROW) | Air-vacuum excavation of 30 utility potholes for the design phase of Tucson DOT Prop 411 Neighborhood St. Improvements Bilby Rd Modernization Project |
TR-ROW-0623-00898 | Complete | 06/22/2023 | 08/27/2023 | UNIT 49 | Right-of-Way (ROW) | Air-vacuum excavation of 30 utility potholes for the design phase of Tucson DOT Prop 411 Neighborhood St. Improvements Bilby Rd Modernization Project |
TR-ROW-0623-00898 | Complete | 06/22/2023 | 08/27/2023 | UNIT 6 | Right-of-Way (ROW) | Air-vacuum excavation of 30 utility potholes for the design phase of Tucson DOT Prop 411 Neighborhood St. Improvements Bilby Rd Modernization Project |
T20CM02842 | Approved | 05/05/2020 | N/A | 06 | Residential Building - One or Two Family | GAS PRESSURE TEST |
TC-COM-0423-01159 | Withdrawn | 04/27/2023 | 10/24/2023 | Commercial Building | Riser on power pole replacement | |
TC-COM-0423-01160 | Issued | 04/27/2023 | 04/14/2024 | Commercial Building | Electrical upgrade on north system of the park | |
T21CM02667 | Expired | 03/24/2021 | 09/21/2021 | 26 | Residential Building - One or Two Family | 8x8 shed |
TR-ROW-0323-00502 | Complete | 03/16/2023 | 05/10/2023 | UNIT 36 | Right-of-Way (ROW) | Perform 7-inch diameter soil borings to depths of approximately 3 feet below existing site grade along Bilby Road between 12th Avenue and Country Club Road to obtain soil samples for a pavement section design |
T20MH00016 | Issued | 03/16/2020 | 09/14/2020 | 11 | Residential Building - One or Two Family | REPM OF M/H |
T20MH00018 | Issued | 03/16/2020 | 09/13/2020 | 40 | Residential Building - One or Two Family | REPLL OF M/H |
T20MH00012 | Issued | 03/05/2020 | 12/07/2020 | 40 | Residential Building - One or Two Family | MOBILE HOME REPL |
T01MH00162 | EXPIRED | 03/16/2001 | 09/25/2001 | #34 | MH | MOBILE HOME:SET UP |
T01PL01817 | FINAL | 09/18/2001 | 04/14/2002 | PLUMB | NEW GAS SERVICE | |
T02PL02040 | FINAL | 11/07/2002 | 05/07/2003 | #36 | PLUMB | NEW:GAS LINE |
T10CM03310 | FINAL | 11/29/2010 | 05/28/2011 | #24 | COMBO | COMPLIANCE:RELOCATE:SHED |
T11CM00731 | WITHDRWN | 03/08/2011 | N/A | #42 | COMBO | ADDT: BEDRM AND BATHRM |
T11CM01177 | WITHDRWN | 04/21/2011 | N/A | #42 | COMBO | ADDITION:BEDROOM/BATHROOM |
T11MH00025 | FINAL | 04/11/2011 | 10/08/2011 | #26 | MH | MOBILE HOME:COMPLIANCE SET UP |
T13MH00054 | FINAL | 10/17/2013 | 04/15/2014 | #43 | MH | MOBILE HOME SET UP |
T14MH00030 | FINAL | 06/09/2014 | 12/06/2014 | #42 | MH | ZON & ENG COMPLIANCE; MH SET UP |
T15MH00084 | EXPIRED | 12/14/2015 | 06/11/2016 | #36 | MH | MH SET UP |
T19CM01236 | FINAL | 02/20/2019 | 08/20/2019 | COMBO | REPAIR RISERFOR OVERHEAD 400 AMP SERVICE FOR METER: TR4R-3100AAPL | |
T19CM06059 | WITHDRWN | 08/22/2019 | N/A | COMBO | MH PLACEMENT | |
T20CM06637 | FINAL | 09/24/2020 | 04/06/2021 | COMBO | REPLACE TWO 200 AMPS LIKE FOR LIKE SUB PANELS | |
T20RW06203 | FINAL | 11/17/2020 | 01/18/2021 | ROW | From TEP Pole N of 1200 E Bilby Rd, head W and begin 164' aerial overlash .625 coax replacing damaged cable. Tie in. | |
T97MH00433 | EXPIRED | 12/04/1997 | 06/13/1998 | #18 | MH | MOBILE HOME:SETUP |
T97MH00434 | EXPIRED | 12/08/1997 | 06/21/1998 | #34 | MH | MOBILE HOME:SETUP |
T98MH00151 | EXPIRED | 03/18/1998 | 09/22/1998 | #34 | MH | MOBILE HOME:SETUP |
Code Enforcement
Address: 1200 E BILBY RD
Date - 11/13/2024 5:48 a.m.
Total Number Of Code Cases - (1)
Case Number | Case Status | Entered Date | Exp Date | Unit | Type | Description |
---|---|---|---|---|---|---|
CE-VIO1222-01056 | Closed - Resolved | 12/22/2022 | 12/22/2022 | UNIT 44 | EMERGENCY CALL OUT FROM TFD, MOBILE HOME FIRE |
Record Requests
Address: 1200 E BILBY RD
Date - 11/13/2024 5:48 a.m.
Total Number Of Requests - (4)
Request Number | Status | Request Date | Completed Date | Type | Description |
---|---|---|---|---|---|
REQ-0123-00882 | Complete | 01/23/2023 | 01/23/2023 | Requests | SCANNED MICROFICHE |
REQ-0523-02878 | Complete | 05/23/2023 | 05/31/2023 | Requests | Riser on power pole replacement |
REQ-0524-03510 | Complete | 05/09/2024 | 05/20/2024 | Requests | south service upgrades including 3 new 200 amp boxes and new gutter with new wire |
REQ-0624-04155 | Submitted - Online | 06/06/2024 | N/A | Requests | south service upgrades including 3 new 200 amp boxes and new gutter with new wire. New plans we are repalcing like for like |