Plan Review Detail
Review Status: Completed
Review Details: PREAPPLICATION LABELS
Plan Number - T22PRE0169
Review Name: PREAPPLICATION LABELS
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 08/03/2022 | JPEELDA1 | COT NON-DSD | FIRE | Completed | Questions: Jennifer Peel-Davis Jennifer.Peel-Davis@Tucsonaz.gov 520-837-7033 Fire Plans Examiner |
| 08/10/2022 | SCABRAL1 | ENGINEERING | REVIEW | Completed | 1. Provide waste stream calculations. 2. Relocate trash dumpster to an appropiate location. Make sure to have an enclosure. Stephen Blood (520) 837-4958 Stephen.blood@tucsonaz.gov |
| 08/10/2022 | AWARNER1 | LANDSCAPE | REVIEW | Completed | CDRC TRANSMITTAL PROJECT: Quad Plex ACTIVITY NO. T22PRE0169 ADDRESS/PARCEL: 5639 E 5th St ZONING: R-3 7.6 Landscaping and Screening The Unified Development Code (UDC) requires all new development or an expansion of greater than 25% of an existing development submit a landscape plan, UDC 7.6.2. Preparation of the landscape plan shall adhere to UDC 7.6.4. and Administrative Manual 2-10. " trees are required to be placed within the north parking areas Placing trees along the edge of a parking area or at the ends of parking row does not meet the intent of the UDC. All spaces within 40' of a tree is only one of the requirements. The intent is to provide as much shade on the asphalt as possible, and the requirement is 1 tree per 4 parking spaces; trees are expected to be placed within the parking area itself to provide shade on asphalt. Trees are to be distributed evenly throughout the parking area, UDC 7.6.4.1.B.1, UDC Technical Standards Manual 5-01-.3.2 and UDC 7.6.4.B.1.a. Commercial Rainwater Harvesting plan is required UDC Technical Standards Manual - Section 4-01.0.0. and Section 5-01.0.0 Landscaping and Screening. Demonstrate maximizing water harvesint If you have any questions about this transmittal, contact Anne Warner, RLA PDSD Landscape/NPPO Review at email anne.warner@tucsonaz.gov |
| 08/10/2022 | SBEASLE1 | TUCSON WATER NEW AREA DEVELOPMENT | REVIEW | Completed | 130 - 200 pm - T22PRE0169 - 5639 E 5TH ST Site: Quad Living 5th 1. Tucson Water's New Area Development Unit has no objections to the proposed development and offers the following comments for your convenience. 2. The existing buildings on this site are supplied water via an existing 3" cement asbestos water main on the north side of the property in Baker Street. 3. This existing 3" water main does not have the capacity necessary to serve any necessary on-site fire hydrants and/or fire suppression sprinkler systems. 4. If on-site fire hydrants and/or fire suppression sprinkler systems must be constructed for this project, they will need to be connected to the existing 12" cement asbestos water main in the south half of 5th St. 5. This project may or may not be affected by Tucson Water's Road Recovery Prop 101 Rehab Pck 5 CIP project, which is currently in the design phase. You may contact Mr. Walter Breitenstein, Tucson Water's Project Manager for this CIP project at walter.breitenstein@tucsonaz.gov for information about this CIP project. 6. The above comments are based on the limited preliminary information provided by the applicant and should not be construed as a complete review of the proposal. Any questions, comments or concerns about these comments may be directed to: Tim Rowe, P.E., Civil Engineer Tucson Water, New Development Section 201 N. Stone Avenue, #2-220 P.O. Box 27210 Tucson, AZ 85726-7210 (520) 837-2106 tim.rowe@tucsonaz.gov |
| 08/11/2022 | SAMUEL ROGERS | ZONING | REVIEW | Completed | CDRC Thursday Pre-Submittal Transmittal PDSD Zoning Review FROM: Samuel Rogers, Planner PROJECT: Thursday Pre-submittal meeting - T22PRE0169 Address: 5639 e 5th ST Parcel(s): 127035430 Zoning: R-3 Existing Use: Medical Service - Outpatient/Multifamily Proposed Use: Multifamily TRANSMITTAL DATE: 08/10/2022 COMMENTS: 1. Development must comply with the Administrative Manual Section 2-06 - Development Package. 2. Multifamily is an allowed use in the R-3 zone is subject to use-specific standard UDC 4.9.7.B.6. 3. If the site is proposed to be expanded by 25% or more the entire site will need to be brought up to code. 4. If the site needs to meet full code compliance, the south parking lot will need to be reconfigured to not back out into the ROW. 5. East 5th St. is a Major Street and Route. 5th St. appears to be at its full width of 90'. Major Street and Route setbacks will apply to an new structures on all street sides. 6. R-3 allows for a maximum density of 36/acre. This site is approximately .78 acres allowing for 28 units, the proposed 20 units do not exceed the density maximum. 7. The required setback on the east and west is 10' or ¾ the height of the structure's wall. 8. The maximum allowed height is 40'. 9. Pedestrian connection will be required from the new units to the adjacent ROW. 10. See engineering comments about the trash enclosure. 11. The comments provided are preliminary and are not to be assumed as a complete review of the proposal. During the Development Package review process, a full review will be made by Zoning to assure compliance with the applicable UDC development criteria and Technical Standards. If you have any questions please contact me at Samuel.Rogers@tucsonaz.gov or (520) 837-6932. |
| 08/15/2022 | DSTIFFE1 | COT NON-DSD | TRAFFIC | Completed | No Comments |