| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 08/08/2022 | SCABRAL1 | ENGINEERING | REVIEW | Passed | |
| 08/10/2022 | STEVE SHIELDS | ZONING | REVIEW | Approved | |
| 08/10/2022 | KEN VAN KARSEN | BUILDING-RESIDENTIAL | REVIEW | Reqs Change | T22CM05955 PLAN REVIEW COMMENTS Plan review for the above referenced structure has been completed. This letter reflects comments to be addressed. In order to facilitate a shorter back check time, please provide an updated complete plan set with a written response to each of the notated items indicating action taken. Do not cloud the changes made for comment revisions. SCOPE OF REVIEW: The scope of this plan review covers architectural, plumbing, mechanical, energy conservation and electrical. All code references are to the 2018 International Residential Code and 2018 International Energy Conservation Code. All features were checked only to the extent allowed by the submittals provided. All portions of this project are assumed to meet or will meet other departmental requirements, conditions and concerns before permit approval. GENERAL REQUIREMENTS: The City of Tucson adopted the 2018 IRC with amendments on 1/1/2019. Show the current code reference on the plans. Update the 2006 IRC reference on the site plan. Consolidate pages of construction plans into a single .PDF file as prescribed at the PDSD web site. Sample plans are available at https://www.tucsonaz.gov/pdsd/residential-permits FOUNDATION PLAN: 1. Dimension the footing length, width, and depth into undisturbed soil for each footing type and condition, R403.1. Show the minimum 12” reinforced footing depth below the undisturbed ground surface R403.1. Show #4 rebar reinforcement with 3” clearance from earth, R403.1.3.5.3. Provide ½” anchor bolts with 7” embedment, R403.1.6. Complete the detail information left blank on Section “A”. SECTIONS - DETAILS: 1. Show the Post Section Detail with #4 rebar in the footing, R403.1. 2. Notate and specify the size of post base with 1” standoff above concrete, R317.1.4 exception 1. 3. Show roof (uplift resistance) rafter fasteners (H2.5) with appropriate uplift capacity, R802.11 amended. ELECTRICAL PLANS: 1. Show the overhead service conductor with an 8-foot clearance above the roof, E3604.2.1 or relocate the service panel from under the roof. The service line change or a new panel location must be coordinated with TEP for approval. Consider moving the electrical service panel to the east corner of the dwelling with a feeder to the existing circuit breaker panel. Please contact the plans reviewer if you have any questions: Ken Van Karsen 520 837-4912 City of Tucson Residential Plan Review |
| 08/29/2022 | AWARNER1 | NPPO | REVIEW | Approved |