Permit Number: T22CM05743
Parcel: 141185400

Review Status: Completed

Review Details: COMMERCIAL - BLDG/FIRE/ZONING/ENG

Permit Number - T22CM05743
Review Name: COMMERCIAL - BLDG/FIRE/ZONING/ENG
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
08/11/2022 PAUL CAMARENA ZONING REVIEW Reqs Change FROM: Paul Camarena
PDSD Zoning Review Section

PROJECT: T22CM05743
Tractor supply store
9848 E OLD VAIL RD Zoning I-2

TRANSMITTAL DATE:?August 11, 2022


COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed.


1.COMMENT: Zoning has reviewed the building plans for compliance with the associated unapproved Development Package DP22-0072. Zoning cannot approve the building plans until the DP is approved.

If you have any questions about this transmittal, Contact Paul Camarena at (520)837-4986 or by email Paul.Camarena@tucsonaz.gov
08/11/2022 PCAMARE1 COMMERCIAL IMPACT FEE COMMERCIAL IMPACT FEE PROCESSING Needs Review
08/13/2022 SAFEBUILT 2ND PARTY REVIEW REVIEW Reqs Change Activity Number: T22CM05743

GENERAL:
Provide written responses to all review comments.
Provide a complete plan set.
Provide additional documents as requested by review staff.


STRUCTURAL REVIEW COMMENTS:
Denied
1. The requirements in OSHA 1926.757 for the erection of open web steel joists are to be followed. Where steel joists are used with columns that are not framed in at least two directions with solid web structural steel members, a steel joist shall be field-bolted at the column to provide lateral stability to the column during erection. Where constructability does not allow a steel joist to be installed at the column the joists are to be stabilized on both sides of the column.
2. Except for steel joists that have been pre-assembled into panels, connections of individual steel joists to steel structures in bays 40 feet or more shall be fabricated to allow for field bolting during erection.
3. Provide a vertical stabilizer plate at columns for steel joist as required by OSHA 1926.757.
4. Verify OSHA steel erection standards for open web steel joists. Section 1926.757 (a)(8) requires connections of individual steel joists to steel structures in bays of 40 feet or more shall be fabricated to allow for field bolting during erection.
5. Show lines of bridging for the steel joists as recommended by the Steel Joists Manufacturer.


BUILDING REVIEW COMMENTS:
Approved


MECHANICAL REVIEW COMMENTS:
Denied
1. You are missing the correction for your outdoor air calculations please correct (IMC2018,403.3.1.1.1.2)sheet M1.0
2. Upon activation the duct smoke detectors must report to the fire alarm panel and must be noted as such (IMC2018,606.4.1) sheet M2.0
3. In the retail sales area you need 3,584 continuous cfm of outdoor air during occupied hours. your notes in the rooftop schedule has the economizer opening by a CO2 detector this is not acceptable and you are missing the correction factor in your calculation sheet M2.0 (IMC2018,403.3.1.1)
4. Upon activation the smoke detector shall shut down all operational capabilities of the air distribution system and shall be noted as such sheet M2.0 (IMC2018,606.4


ELECTRICAL REVIEW COMMENTS
Denied
1. Sheet E1.0: Occupant sensor controls shall be installed in storage rooms ( STOCKROOM 105A) 2008 IECC, C405.2.1
2. Sheet E1.0: Show luminaire control / switch for PETWASH 112 room.
3. Sheet E1.0: Show a note on lighting sheet to provide direction for compliance with 2018 IECC, C408.3.1 functional testing of lighting controls.
4. Sheet E1.0: Show a note on lighting sheet to provide direction on documentation requirements in 2018 IECC, C408.3.2
5. Show ampacity for B-21 circuit conductors comply with ampacity for conductors in raceways exposed to sunlight on rooftops NEC 2017, 310.15(B)(3)(c)
6. Sheet E2.0, E4.0, ES1.0:Show compliance with 2018 IECC, C405.9 voltage drop requirements for feeders and branch circuits.
7. Sheet E4.0: For 400A service disconnect (items 15 on riser diagram), show maximum available fault current calculation and date calculation was performed. NEC 2017 110.24.
8. Sheet E4.0: Show conductor and raceway sizes for conductors from transformer disconnect to transformer.


PLUMBING REVIEW COMMENTS:
Denied
First Plumbing Review:
1). Add gutter & downspout sizing calculations to plan page A7.0 - IPC 1106.1, 1106.3, 1106.6
2). All hose bibs on plan page P1.0 need individual shut off valves. -IPC 606.2


If you require additional clarification regarding these comments, please contact Doris Benoit at doris.benoit@tucsonaz.gov
08/15/2022 JVINCEN1 FIRE REVIEW Approved
08/29/2022 ROBERT SHERRY WATER REVIEW Completed
08/31/2022 LOREN MAKUS ENGINEERING REVIEW Reqs Change This cannot be approved until the Development Package is approved.
Make sure the building roof drainage matches the Developement Package drainage scheme.

Loren Makus
Loren.Makus@TucsonAz.gov

Final Status

Task End Date Reviewer's Name Type of Review Description
08/31/2022 NGARCIA3 OUT TO CUSTOMER Completed