Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Completed
Review Details: RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO
Permit Number - T22CM05531
Review Name: RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
07/21/2022 | IMONSHI1 | ENGINEERING | REVIEW | Passed | |
07/27/2022 | IMONSHI1 | ZONING | REVIEW | Approved | |
07/27/2022 | IMONSHI1 | NPPO | REVIEW | Passed | |
08/11/2022 | SAFEBUILT | 2ND PARTY REVIEW | REVIEW | Reqs Change | Activity Number: T22CM05531 GENERAL: Provide written responses to all review comments. Provide a complete plan set. Provide additional documents as requested by review staff. STRUCTURAL REVIEW COMMENTS: Denied A. Sheet 5: Reference 2018 IRC Section R506.2.3. Revise drawings to include a 6-mil polyethylene or approved vapor retarder with joints lapped not less than 6 inches placed between the concrete slab and the base course or prepared subgrade. B. Sheet 2: Reference 2018 IRC Section 602.10. Please indicate intentions with regard to bracing of the 11’ exterior braced wall line segment on the south elevation of the new master bedroom. BUILDING REVIEW COMMENTS: Denied Sheets 3 & 5: Reference 2018 IRC Section R806. Pleased provide information regarding intentions for attic ventilation. MECHANICAL REVIEW COMMENTS: Denied A. Sheet 4 (Mechanical Plan): Reference 2018 IRC Section M1411.3 Condensate disposal, as amended. Condensate disposal shall be allowed to terminate as follows: 1. Into an approved fixture tailpiece, funnel drain, waste air gap fitting, floor sink, slop sink and laundry tray. 2. At or below grade outside the building in an area capable of absorbing the condensate flow without surface drainage. 3. Over roof drains or gutters or downspouts that connect to drainage pipes, provided they terminate at or above grade in an area capable of absorbing the condensate flow without surface drainage. Current plans do not specify how condensate from the heat pump unit will be handled. B. Sheet 4 (Mechanical Plan): Reference 2018 IRC Section M1502.3. Ensure that clothes dryer exhaust terminates on the outside of the building and not less than 3 feet from any openings. ELECTRICAL REVIEW COMMENTS Denied Sheet 4 (Electrical Plan): Reference 2018 IRC Section E4101.5. Provide electrical disconnect for exterior heat pump equipment. The disconnect must be in sight of the equipment. PLUMBING REVIEW COMMENTS: Approved If you require additional clarification regarding these comments, please contact Doris Benoit at doris.benoit@tucsonaz.gov |