Review Status: Completed
Review Details: COMMERCIAL - BLDG/FIRE/ZONING/ENG
Permit Number - T22CM05472
Review Name: COMMERCIAL - BLDG/FIRE/ZONING/ENG
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
08/01/2022 | SAFEBUILT | 2ND PARTY REVIEW | REVIEW | Reqs Change | Activity Number: T22CM05472 GENERAL: Provide written responses to all review comments. Provide a complete plan set. Provide additional documents as requested by review staff. STRUCTURAL REVIEW COMMENTS: Approved BUILDING REVIEW COMMENTS: Denied 1. Provide clarification about the adjacent tenants to ensure proper separation is provided. 2. The restroom is accessed through the storage area. Restroom access is not permitted through storage toms. Provide properly accessible restrooms in accordance with Section 2902.3.1. 3. Provide additional details regarding the egress onto the loading dock. Provide stair details to ensure they meet all the applicable requirements of Section 1011. 4. Provide a narrative on the storage approach. Provide the class of combustibles present and evidence of compliance of all applicable requirements. MECHANICAL REVIEW COMMENTS: Denied 1. Please provide a COMcheck that indicates compliance for new mechanical system and scan that data onto one of the mechanical sheets. This provides evidence the mechanical system is in compliance. ELECTRICAL REVIEW COMMENTS Approved PLUMBING REVIEW COMMENTS: Approved If you require additional clarification regarding these comments, please contact Doris Benoit at doris.benoit@tucsonaz.gov |
08/04/2022 | WBERGER1 | ENGINEERING | REVIEW | Passed | |
08/04/2022 | WBERGER1 | ZONING | REVIEW | Approved | |
08/04/2022 | WBERGER1 | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Passed | |
08/18/2022 | ROBERT SHERRY | WATER | REVIEW | Completed | |
09/15/2022 | PSHELTO1 | FIRE | REVIEW | Approved |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
09/15/2022 | VVERA1 | OUT TO CUSTOMER | Completed |