| 06/22/2022 | WBERGER1 | ZONING | REVIEW | Approved | |
| 06/22/2022 | KEN VAN KARSEN | BUILDING-RESIDENTIAL | REVIEW | Reqs Change | T22CM04184 PLAN REVIEW COMMENTS Plan review for the above referenced structure has been completed. This letter reflects comments to be addressed. For facilitating a shorter back check time, please provide an updated complete plan set with a written response to each of the notated items indicating action taken. Do not cloud the changes made for comment revisions. SCOPE OF REVIEW: The scope of this plan review covers architectural, plumbing, mechanical, energy conservation and electrical. All code references are to the 2018 International Residential Code and 2018 International Energy Conservation Code. All features were checked only to the extent allowed by the submittals provided. All portions of this project are assumed to meet or will meet Zoning and other departmental requirements, conditions and concerns before permit approval. GENERAL REQUIREMENTS: The City of Tucson adopted the 2018 IRC with amendments on 1/1/2019. Show the current code reference on the plans. GENERAL COMMENTS: 1. All SFR and Duplex plans submitted after March 1, 2009 require a solar water system, or future installation preparation City of Tucson Ordinance #10549 with one of the following provisions: ½”control conduit and two ¾” copper piping for water with rooftop termination; straight 3” capped sleeve; or an accessible attic (clear path 30” wide x 30” high) over the water heater. Show appropriate notation. 2. All SFR and Duplex plans submitted after July 1, 2009, require a solar photo-voltaic system, or future installation preparation City of Tucson Ordinance #10549 . a. Show a minimum 300 SF clear solar-ready zone on a roof or framing plan, T103.3. Model plans should show four typical south facing roof surfaces. b. Label a double breaker space for future Photo Voltaic on the panel schedule opposite end from the main/supply side, T103.9. Update breaker location to opposite end from main breaker. 3. All construction drawings submitted after June 1, 2010, for one- or two-family dwellings must provide gray water utilization or preparation, Ordinance #10579/11089 revised July 9, 2013. The ordinance revision now requires a gray drain line discharge from one fixture for a one-story dwelling. Additional gray fixture drains are optional. Show a second clothes washer standpipe plumbed to an exterior wall above grade when feasible, or a single bathing fixture drain looped 3’ beyond an exterior wall below grade before connection to the building drain. See details for compliance at https://www.tucsonaz.gov/pdsd/water-energy-conservation FOUNDATION PLANS: 1. Show interior braced wall panels with foundation anchor bolt connection to bottom plates, R602.10.8.3 and R403.1.6. FLOOR PLANS: 1. Show a maximum ½” floor elevation changes at a notated accessible route entrance on the floor plan, R106.1.1. Include all threshold conditions for a route from the exterior into the living space. STRUCTURAL PLANS: 1. Provide a complete braced wall design, R602.10 include: a. Braced wall lines with maximum spacing of 60’ and offsets no more than 4’. b. Braced wall panel within 10’ of each end and no more than 20’ between edges. 2. Show braced wall panel compliance for framed walls with a garage door opening, Table R602.10.5. For prescriptive braced wall structures show a portal frame with hold-downs PFH method, Figure R602.10.6.2, or a portal frame at garage door PFG method, Figure R602.10.6.3, or a continuously sheathed portal frame CS-PF method, Figure R602.10.6.4. If you have any questions, please contact: Ken Van Karsen (520) 837-4912 City of Tucson Residential Plan Review |
| 07/01/2022 | AWARNER1 | NPPO | REVIEW | Approved | |
| 07/11/2022 | LSHAMIS1 | FIRE | REVIEW | Reqs Change | Fire sprinkler shall be installed in the house. Cover sheet shall show that fire sprinklers are being installed and plans will be submitted to TFD and a permit obtained. Questions: Jennifer Peel-Davis Jennifer.Peel-Davis@Tucsonaz.gov 520-837-7033 Tucson Fire Department Fire Plans Examiner |
| 07/11/2022 | SBLOOD1 | ENGINEERING | REVIEW | Approved |