Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - BLDG/FIRE/ZONING/ENG
Permit Number - T22CM03945
Review Name: COMMERCIAL - BLDG/FIRE/ZONING/ENG
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
06/09/2022 | SAFEBUILT | 2ND PARTY REVIEW | REVIEW | Reqs Change | Activity Number: T22CM03945 GENERAL: Provide written responses to all review comments. Provide a complete plan set. Provide additional documents as requested by review staff. STRUCTURAL REVIEW COMMENTS: Denied 1. The Enercalc Calculations submitted have certain Foundations shown as Failing. Some Foundations sizes shown on the calculations does not match with what is shown on the Drawing. Revise Drawings to match with Structural Calculations and Revise Calculations which are failing. Each foundation calculations to match exact location on the drawing and resubmit. 2. Provide Geotechnical Report for the proposed building per International Building Code 2018, Section 1803.1. BUILDING REVIEW COMMENTS: Denied 1. Sheet G003: Several pieces of information are missing from the project data box. Provide all necessary information. 2. Sheet G-006: Provide the UL assembly chosen for the separation between the fabrication area and the office. It's assumed wall type W4 is being used for that separation. There are no wall tags provided for this separation wall on the enlarged floor plans. Provide the proper assembly and wall tags. 3. Sheet A-101: Windows are not permitted in fire barriers separating occupancies in accordance with Table 716.1(3). 4. Sheet A-101: The doors located in the fire barrier separating the occupancies are not rated properly. Provide properly rated doors in accordance with Table 716.1(2). MECHANICAL REVIEW COMMENTS: Denied 1. Provide ventilation air schedule for all occupancies, and include how you are ventilating the warehouse (IMC2018,403.3.1.1.1) 1.Provide ventilation calculations (IMC2018,,403.3.1.1.1) to show how you are going to meet the 4% openable area to the outdoors for natural ventilation 2. Provide a detailed narrative on the process that occurs in the warehouse (e.g. what materials are you storing in the warehouse, what type of forklifts are you using in the warehouse is it fuel or electric) (imc2018,106.3.1) ELECTRICAL REVIEW COMMENTS Denied E-101 OVERALL ELECTRICAL FLOOR PLAN: Need to provide an Interior lighting Comcheck for whole interior to prove 2018 IECC compliance. E-300 ONE-LINE DIAGRAM: Full wire AWG values not shown in pdf panel schedules. Should correct. MDP Panel schedule states it is MLO, but Single-Line shows MCB. Design should be consistent, call out one or other. Electrical Keyed Note #5 calls for 4 conductors. Only needs to be 3 conductors plus ground as it feeds a Delta-wye xfmr. Should correct. PLUMBING REVIEW COMMENTS: Denied First Plumbing Review: 1). Plan page C-209 missing (need to see sewer continuation). -IPC 106.3.1 2). Add gutter & down spout sizes with calculations to plan page A-104 -IPC 1106.1, 1106.3, 1106.6 3). This occupancy type & load requires a High/Low drinking Fountain. -IPC 403.1 4). Will Osha require An eyewash & or emergency shower for this facility? 5). water heater detail #11 on plan P-500 shows floor mounted installation, all other plumbing pages show elevated water heater. Plan pages need to correlate if elevated show support requirements & add pan to detail #11. -IPC 106.3.1 , 504.7 If you require additional clarification regarding these comments, please contact Doris Benoit at doris.benoit@tucsonaz.gov |
06/15/2022 | ROBERT SHERRY | WATER | REVIEW | Completed | |
06/23/2022 | PAUL CAMARENA | ZONING | REVIEW | Reqs Change | REVIEW TRANSMITTAL FROM: Paul Camarena PDSD Zoning Review Section PROJECT: T22CM03945 Building Plans (1st Review) 4711 E VALENCIA RD Zoning PAD-21 TRANSMITTAL: June 23, 2022 1. Zoning has reviewed the building plans for compliance with the associated unapproved Development Package DP22-0147. Zoning cannot approve the building plans until the DP is approved. If you have any questions about this transmittal, Contact Paul Camarena at (520)837-4986 or by email Paul.Camarena@tucsonaz.gov |
06/23/2022 | PCAMARE1 | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Needs Review | |
06/28/2022 | SSHIELD1 | ENGINEERING | REVIEW | Reqs Change | See Zoning comments |
07/07/2022 | JVINCEN1 | FIRE | REVIEW | Approved | Building is 27,700 sq feet and has a fire flow requirement of 3,500 GPM. Building shall have a fire sprinkler system installed thoughout. DP shall be approved prior to CM being approved by TFD. Questions: Jennifer Peel-Davis Jennifer.Peel-Davis@Tucsonaz.gov 520-837-7033 Fire Plans Examiner Tucson Fire Department |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
07/07/2022 | VVERA1 | OUT TO CUSTOMER | Completed |