Permit Review Detail
Review Status: Completed
Review Details: RESUBMITTAL
Permit Number - T22CM02822
Review Name: RESUBMITTAL
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 06/14/2022 | JPEELDA1 | FIRE | REVIEW | Approved | |
| 06/16/2022 | DBENOIT1 | 2ND PARTY REVIEW | REVIEW | Reqs Change | Activity Number: T22CM02822 GENERAL: Provide written responses to all review comments. Provide a complete plan set. Provide additional documents as requested by review staff. STRUCTURAL REVIEW COMMENTS: Approved BUILDING REVIEW COMMENTS: Approved MECHANICAL REVIEW COMMENTS: Denied 1. Return air shall be approximately the same as supply air. Provide more return air grills sheet M1 (IMC 2018 403.1 & 601.5 item 4) Response: Additional return air grilles are not required. Return air grilles and ductwork are designed by a registered design professional and meet code requirements. Not Complied you have no return air grilles in the waiting room and phot rooms. 2. Provide cfm ratings for all return air grills sheet M1 (IMC 2018, 206.3.1) Response: CFM ratings are provided for return air grilles in the ambulatory occupancy side of the building. CFM ratings are not required to balance the return grilles for the medical office occupancy side of the building. Not Complied. 1. the air balance report is required for both sides and 2 sufficient return air is addressed in the code, and that is why, this information is required in the review process. 3. Show where this bathroom exhaust duct is terminating sheet M1 (IMC 2018, 106.3.1) Response: All restrooms have exhaust duct routed to terminate at rooftop exhaust fans or inline fans ducted to terminate at roof caps. This is shown on sheet M1 and M2. Complied 4. Where equipment or appliances requiring access are located higher than 16’ above grade a permanent ladder or roof hatch shall be installed sheet M2 (IMC2018, 306.5) Response: Comply. Refer to architectural Complied ELECTRICAL REVIEW COMMENTS Approved PLUMBING REVIEW COMMENTS: Conditionally Approved Second Plumbing Review: 1 thru 8 OK 9). OK-Field Verify Floor sink Trap seal protection, Missing From fixture schedule 10 thru 12 OP If you require additional clarification regarding these comments, please contact Doris Benoit at doris.benoit@tucsonaz.gov |