Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Number: T22CM02001
Parcel: 11612151B

Review Status: Completed

Review Details: COMMERCIAL - TI

Permit Number - T22CM02001
Review Name: COMMERCIAL - TI
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
03/29/2022 ERIC NEWCOMB BUILDING-COMMERCIAL REVIEW Approved
03/31/2022 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Reqs Change 1. The dwelling unit previously had an evaporative cooler, not an air conditioner. Provide specifications for the proposed HVAC unit and a heating/cooling load calculation to verify the required unit capacity.
2. Revise the window specifications to require a maximum U-factor of 0.40 and a maximum SHGC of 0.25.
03/31/2022 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Passed
03/31/2022 ROBERT SHERRY WATER REVIEW Passed
04/03/2022 JVINCEN1 FIRE REVIEW Approved
04/05/2022 STEVE SHIELDS ZONING REVIEW Approved
04/05/2022 SSHIELD1 ENGINEERING REVIEW Passed
04/05/2022 SSHIELD1 COMMERCIAL IMPACT FEE COMMERCIAL IMPACT FEE PROCESSING Passed
04/14/2022 DAN SANTA CRUZ ELECTRICAL-COMMERCIAL REVIEW Reqs Change Please address the electrical plan review comments and provide a written response.

1. Ref; Plan Sheet E0.1, ELECTRICAL SPECIFICATIONS. This multifamily site is considered commercial. Please change the electrical code reference to 2017 NEC.

2. What is a NEMA 13R disconnect? Shown for the AC unit outside the building. NEMA 13 enclosures are not normally installed outdoors. Did you mean a NEMA 3R disconnect?

3. Is everything electrical being replaced? Please indicate what is existing to remain and what is new.

4. Show the location of the Breaker Panel. If its being replaced, do not install in the closet or bathroom. NEC 240.24A-thru-F.

5. Provide compliance with the 2018 IECC for the lighting. R404.1.

6. Provide complete compliance with the 2012 Tucson/Pima County Outdoor Lighting Code. See section 104 for plan submittal requirements.

7. Show luminaire, ceiling fans, or receptacle switching circuitry on the lighting and or power plan.

Ref; 2018 IBC section 107.1, 2017 NEC, City of Tucson Commercial Plan Submittal Requirements