Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
02/16/2022 | ROBERT SHERRY | WATER | REVIEW | Completed | |
02/25/2022 | JPEELDA1 | FIRE | REVIEW | Approved | |
02/28/2022 | SAFEBUILT | 2ND PARTY REVIEW | REVIEW | Reqs Change | Activity Number: T22CM00730 GENERAL: Provide written responses to all review comments. Provide a complete plan set. Provide additional documents as requested by review staff. STRUCTURAL REVIEW COMMENTS: Approved BUILDING REVIEW COMMENTS: Denied 1. Sheet 2g2.1: The occupant load calculations are not correct. The training room and the break room would be considered an assembly space. This may require additional exits. Provide corrected occupant load calculations in accordance with Table 1004.5. 2. The travel on the stairs must be included in the travel distance to the exit. MECHANICAL REVIEW COMMENTS: Conditionally Approved 1. Approved/Subject to field approval ELECTRICAL REVIEW COMMENTS Approved PLUMBING REVIEW COMMENTS: Denied 1). Add gutter sizes for Roofs E & F to calculation table on plan page 3A3.0 2). Show the lavatory center to side wall distance & the multiple lav center to separation distances to plan pages 1P1.0 & 2P2.1. -IPC 405.3.1 3). Service Sink is required update all affected pages. If existing show locations. - IPC 403.1 4). Sanitary Riser diagram #2 on P1.1 is illustrating incorrect direction of flow. -IPC 706.3 |
03/03/2022 | STEVE SHIELDS | ZONING | REVIEW | Reqs Change | FROM: PDSD Zoning Review PROJECT: T22CM00730 3950 E Irvington Rd – PAD-34 TEP Warehouse Addition (1st Review) TRANSMITTAL: March 3, 2022 This site is located in the PAD-34 1. Zoning has reviewed the building plans for compliance with DP21-0273 but until the DP is approved Zoning cannot approve the building plan. If you have any questions about this transmittal, please contact Zone1.desk@tucsonaz.gov. |
03/03/2022 | SSHIELD1 | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Completed | |
03/18/2022 | SBLOOD1 | ENGINEERING | REVIEW | Approved |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
03/18/2022 | VVERA1 | OUT TO CUSTOMER | Completed |