Plan Number: T21PRE0119
Parcel: Unknown

Review Status: Active

Review Details: PREAPPLICATION MEETING

Plan Number - T21PRE0119
Review Name: PREAPPLICATION MEETING
Review Status: Active
Review Date Reviewer's Name Type of Review Description Status Comments
05/25/2021 JOHN BEALL M&C Public Hearing 4 Plan Amendment Set M&C Public Hearing Date Active
05/25/2021 BILLIE LEE COMMENTS COMMENTS Active
05/26/2021 ELISA HAMBLIN ZONING REVIEW Completed 1. As the development will have two phases, only one of which requires a rezoning, ensure all development standards can be met on each phase.
2. Submittal of a development package with a subsequent revision for phase 2 will likely be the most efficient approach.

Elisa Hamblin, AICP
Site Review Section Manager
Contact me with questions at elisa.hamblin@tucsonaz.gov
05/26/2021 LOREN MAKUS ELECTRICAL ENGINEERING REVIEW Completed 1. After June 1, the entire site will be considered balanced basin and balanced basin detention will be required.
2. The mapped watercourses through the site must be evaluated. If they have regulatory flow, floodplain permitting and riparian protection will be required.
06/01/2021 MROSS2 FIRE REVIEW Completed -Hydrants required throughout the property
-Automatic fire sprinklers will be required
-Fire alarm system witll be required
-Fire department access road must extend to within 150' of all portions of every building

Michael Ross
520-837-7082
Michael.Ross2@tucsonaz.gov