Plan Review Detail
Review Status: Active
Review Details: PREAPPLICATION MEETING
Plan Number - T21PRE0119
Review Name: PREAPPLICATION MEETING
Review Status: Active
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 05/25/2021 | JOHN BEALL | M&C Public Hearing 4 Plan Amendment | Set M&C Public Hearing Date | Active | |
| 05/25/2021 | BILLIE LEE | COMMENTS | COMMENTS | Active | |
| 05/26/2021 | ELISA HAMBLIN | ZONING | REVIEW | Completed | 1. As the development will have two phases, only one of which requires a rezoning, ensure all development standards can be met on each phase. 2. Submittal of a development package with a subsequent revision for phase 2 will likely be the most efficient approach. Elisa Hamblin, AICP Site Review Section Manager Contact me with questions at elisa.hamblin@tucsonaz.gov |
| 05/26/2021 | LOREN MAKUS | ELECTRICAL ENGINEERING | REVIEW | Completed | 1. After June 1, the entire site will be considered balanced basin and balanced basin detention will be required. 2. The mapped watercourses through the site must be evaluated. If they have regulatory flow, floodplain permitting and riparian protection will be required. |
| 06/01/2021 | MROSS2 | FIRE | REVIEW | Completed | -Hydrants required throughout the property -Automatic fire sprinklers will be required -Fire alarm system witll be required -Fire department access road must extend to within 150' of all portions of every building Michael Ross 520-837-7082 Michael.Ross2@tucsonaz.gov |