Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Plan Review Detail
Review Status: Completed
Review Details: PREAPPLICATION LABELS
Plan Number - T21PRE0116
Review Name: PREAPPLICATION LABELS
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 05/19/2021 | AWARNER1 | LANDSCAPE | REVIEW | Completed | CDRC TRANSMITTAL TO: Planning and Development Services Department, Plans Coordination FROM: Anne Warner, RLA PDSD Landscape/NPPO Review PROJECT: Warehouse Facility T21PRE0116 TRANSMITTAL DATE: May 19, 2021 UDC Article 7.6 Landscaping and Screening The Unified Development Code (UDC) requires all new development or an expansion of greater than 25% of an existing development submit a landscape plan, UDC 7.6.2. Preparation of the landscape plan shall adhere to UDC 7.6.4. and Administrative Manual 2-10. UDC Article 7.7. Native Plant Preservation An approved Native Plant Preservation Plan Sections 7.7.4 is required or a request for an exception from the Native Plant Preservation requirements in accordance with Sections 7.7.3.D.3 & .4 of the Unified Development Code (UDC) is required prior to Grading Plan approval. UDC Technical Standards Manual – Section 4-01.0.0. Commercial Rainwater Harvesting and Section 5-01.0.0 Landscaping and Screening If you have any questions about this transmittal, Contact Anne Warner at (520) 837-4969 or by email anne.warner@tucsonaz.gov |
| 05/19/2021 | MROSS2 | COT NON-DSD | FIRE | Completed | 1. Automatic sprinkler system will be required. 2. Fire alarm system will be required. 3. CO2 system must comply with IFC chapter 53 4. Fire apparatus access roads shall be asphalt or concrete, capable of supporting apparatus up to 75,000 pounds. Michael Ross 520-837-7082 Michael.Ross2@tucsonaz.gov |
| 05/21/2021 | LOREN MAKUS | ENGINEERING | REVIEW | Completed | T21PRE0116 - 1. Site is in a balanced basin. Balanced basin detention and 5-year threshold retention is required. 2. Development plans submitted after June 1 must meet the standards in the newly adopted retention/detention manual: https://www.tucsonaz.gov/pdsd/codes-plans 3. Maximize water harvesting. |
| 05/25/2021 | JVWINKL1 | COT NON-DSD | TRAFFIC | Completed | T21PRE0116 1) New access off S Old Vail Rd will need to meet City of Tucson Access Management Guidelines for width and radius. New curb access ramps on either side according to PAG 207 2) Any out of compliance sidewalk along projects frontage on S Old Vail Rd will need to be replaced according to PAG 203 3) Please provide an estimate of the anticipated trip generation 4) Plans will need to show that the turning movements of the largest expected vehicles can enter off of S Old Vail Road and not impact adjacent travel lanes John Van Winkle, P.E. John.VanWinkle@tucsonaz.gov |
| 05/26/2021 | SBEASLE1 | TUCSON WATER NEW AREA DEVELOPMENT | REVIEW | Completed | 150 - 210 pm - T21PRE0116 - Parcel 141-11-026A - Site Lot 3, Sunbelt Industrial Center 1. Tucson Water has no objections to the proposed development. 2. An existing 12" cement asbestos water main stub constructed under PN 026-1986 extends onto this property from the existing 16" water transmission line in S. Old Vail Rd. 3. The proposed fire loop shown on the detail drawing will need to be public water mains, and be reviewed and approved in Tucson Water's Master Water Plan and Design Plan processes. Eight (8) inch fire hydrants will be required. 4. Any questions, comments or concerns about these comments may be directed to: Tim Rowe, P.E., Civil Engineer Tucson Water, New Development Section 310 W. Alameda St. P.O. Box 27210 Tucson, AZ 85726-7210 (520) 837-2106 |
| 05/27/2021 | SAMUEL ROGERS | ZONING | REVIEW | Completed | CDRC Thursday Pre-Submittal Transmittal PDSD Zoning Review FROM: Samuel Rogers, Planner PROJECT: Thursday Pre-submittal meeting – T21PRE0116 Address: N/A Parcel(s): 141-11-026A and 141-11-026B Zoning: I-1/I-2 Existing Use: Vacant Proposed Use: Marijuana Dispensary Off-site Cultivation Location TRANSMITTAL DATE: COMMENTS: 1. Development must comply with the Administrative Manual Section 2-06 - Development Package. 2. An address will need to be assigned by Pima County Addressing before a permit can be started. 3. Per the application this development includes two parcels, these parcels must be combined. Provide proof that a lot combo application had been accepted by the county during the Development Package (DP) process. 4. The proposed use is Marijuana Dispensary Off-site Cultivation Location and is subject to Use Specific Standards 4.9.9.E.4 and 4.9.13.Q. 5. In the P-I, I-1 and I-2 zones, there is no size limit. 6. In the I-1 and I-2 zones, a marijuana dispensary off-site cultivation location, or a marijuana dispensary off-site manufacturing location in the P-1, I-1, and I-2 zones, shall be located in a permanent, enclosed, locked facility in accordance with state statutes and Arizona Department of Health Services rules and shall not be located in a trailer, cargo container, mobile or modular unit, mobile home, recreational vehicle, or other motor vehicle. 7. In the I-1 and I-2 zones, a marijuana dispensary off-site cultivation location, or a marijuana dispensary off-site manufacturing location in the P-1, I-1, and I-2 zones, shall be setback a minimum of 500 feet from a K-12 public, private, or charter school, measured in a straight and direct horizontal line from the closest exterior or applicable interior suite wall of the marijuana off-site cultivation location to the closest property line of a school. 8. A marijuana off-site cultivation location or a marijuana dispensary off-site manufacturing location and associated uses such as infusion kitchens, shall comply with all lawful, applicable health regulations, including those promulgated by the Arizona Department of Health Services and any other authorized regulatory agency. 9. A marijuana dispensary off-site cultivation location or marijuana dispensary off-site manufacturing location shall provide only wholesale products to other marijuana dispensaries, marijuana dispensary off-site manufacturing locations, or marijuana dispensary off-site cultivation locations. 10. An odor mitigation plan shall be submitted demonstrating compliance with odor control requirements. 11. This site has split I-1 and I-2 zoning. Per Table 6.3-5.B: Exceptions To The P-I, I-1, & I-2 Dimensional Standards in the I-2 zone Medical Marijuana Dispensary Off-Site Cultivation Location have a max height of 75' and a minimum setback of 1½(H) to residential zones. (This exception to the Dimensional Standards brings requirements in line with the I-1 zone). 12. Parking is required at 1 space per 2,000 sq. ft. of storage area for the first 20,000 sq. ft. of storage area plus 1 space per 10,000 sq. ft. of storage area for over 20,000 sq. ft. of storage area, with a minimum of 2 spaces. 13. Land Use Classes which by their nature will not be used for public pedestrian access, such as industrial uses, commercial storage uses, wholesale uses, contractor yards, or similar uses, are not required to have sidewalks constructed, provided adequate pedestrian refuge areas are provided. Pedestrian circulation will still be required. 14. The comments provided are preliminary and are not to be assumed as a complete review of the proposal. During the Development Package review process, a full review will be made by Zoning to assure compliance with the applicable UDC development criteria and Technical Standards. If you have any questions please contact me at Samuel.Rogers@tucsonaz.gov or (520) 837-6932. |