Permit Number: T21CM09727
Parcel: 108254660

Review Status: Completed

Review Details: COMMERCIAL - NEW

Permit Number - T21CM09727
Review Name: COMMERCIAL - NEW
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
03/01/2022 JPEELDA1 FIRE REVIEW Approved
03/02/2022 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Reqs Change 1. Provide a site plan showing the installation of the water service to the building and the installation of the building sewer. Reference: Sections 107.2.1 and 107.2.6, IBC 2018.
2. Horizontal branches shall connect no closer than ten diameters downstream of the bases of vertical stacks. Reference: Section 704.3, IPC 2018.
3. Provide the rim elevation of the next upstream sanitary manhole and the first-floor elevation. Determine the need for a backwater valve per Section 714.1, IPC 2018, as amended by the City of Tucson.
4. Provide secondary (overflow) roof drainage for the four proposed roof scuppers. Reference: Sections 1108.1, 1108.2 and 1108.3, IPC 2018.
03/02/2022 ROBERT SHERRY WATER REVIEW Reqs Change Tucson Water will not allow multiple water meters to serve a single apartment building
03/03/2022 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Reqs Change 1. Provide mechanical ventilation for each apartment per Section 403.1 and 403.3, IMC 2018. Reference: Section R403.6, IECC 2018.
2. Ventilation for kitchens in private dwellings requires a minimum of 25 CFM (continuous operation) or 100 CFM (intermittent operation) of mechanical exhaust per room with no recirculation of air. Reference: Table 403.3.2.3, IMC 2018.
03/03/2022 STEVE SHIELDS ZONING REVIEW Approved
03/03/2022 SSHIELD1 COMMERCIAL IMPACT FEE COMMERCIAL IMPACT FEE PROCESSING Completed
03/07/2022 ERIC NEWCOMB BUILDING-COMMERCIAL REVIEW Approved
03/09/2022 DAN SANTA CRUZ ELECTRICAL-COMMERCIAL REVIEW Passed
03/16/2022 LOREN MAKUS ENGINEERING REVIEW Approved

Final Status

Task End Date Reviewer's Name Type of Review Description
03/16/2022 NGARCIA3 OUT TO CUSTOMER Completed