Permit Number: T21CM09672
Parcel: 10604072A

Address:
218 E PRINCE RD

Review Status: Completed

Review Details: RESUBMITTAL

Permit Number - T21CM09672
Review Name: RESUBMITTAL
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
04/18/2022 SAFEBUILT 2ND PARTY REVIEW REVIEW Reqs Change Activity Number: T21CM09672


GENERAL:
Provide written responses to all review comments.
Provide a complete plan set.
Provide additional documents as requested by review staff.


STRUCTURAL REVIEW COMMENTS:
Approved

BUILDING REVIEW COMMENTS:
Approved

MECHANICAL REVIEW COMMENTS:
Conditionally Approved
Approved/Subject to field approval

ELECTRICAL REVIEW COMMENTS
Approved

PLUMBING REVIEW COMMENTS:
Denied
1). OK-. The New restroom on Plan pages P1.1 & A1.0 can't open directly into the kitchen area -IPC 403.3.2 (PLAN PAGE A1.0 HAS BEEN UPDATED)
2). SAME-Due to the quantity & type of items required to connect to the grease system in this establishment a hydromechanical grease interceptor can't be used. Update plan pages P1.1 & P3.0. with a gravity type grease interceptor - Tucson Amendment IPC 1003.3 See Tuscon amendment below Hydromechanical grease interceptors.
Hydromechanical grease interceptors (HGI), which are generally installed inside, may be used when there are four (4) or fewer fixtures. The minimum size HGI to be installed shall be rated no smaller than 25 gallon per minute with a 50 pound grease capacity. Flow Control devices shall be designed and installed so that the total flow through such devices shall at no time be greater than the rated flow.
Exception: If a dishwasher or food waste disposal unit is used in the facility, an HGI (hydromechanical)cannot be used and an appropriately sized GGI (Gravity Grease Interceptor) or alternative pretreatment device, capable of accepting these wastes, must be installed.
**Approval documentation as stated in response sheet needs to be uploaded with submittal
3). SAME-The K4 ice machine can't discharge to the grease system, Update P1.1 & P1.3 -IPC 1003.2**Approval documentation as stated in response needs to be uploaded with submittal
4). SAME PENDING SOLUTION TO COMMENT #2- . Add Grease interceptor sizing calculations to plan pg. P3.0 -IPC 1003.3.7
5 thru 8 OK


If you require additional clarification regarding these comments, please contact Doris Benoit at doris.benoit@tucsonaz.gov
04/20/2022 SSHIELD1 COMMERCIAL IMPACT FEE COMMERCIAL IMPACT FEE PROCESSING Completed
04/20/2022 STEVE SHIELDS ZONING REVIEW Approved
07/11/2022 LOREN MAKUS ENGINEERING REVIEW Approved