Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - NEW
Permit Number - T21CM09423
Review Name: COMMERCIAL - NEW
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 01/03/2022 | SSHIELD1 | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Needs Review | |
| 01/03/2022 | STEVE SHIELDS | ZONING | REVIEW | Reqs Change | ZONING REVIEW TRANSMITTAL FROM: PDSD Zoning Review PROJECT: T21CM09423 2960 N Campbell Ave – C-1 New Food Service (1st Review) TRANSMITTAL DATE: January 3, 2022 DUE DATE: January 6, 2022 This site is located in the C-1 zone (UDC 4.7.20). Food Service is an allowed use in the zone (UDC Table 4.8-4) subject to Use Specific Standards 4.9.4.M.1 & 5 and 4.9.13.O. 1. Zoning has reviewed the building plans for compliance with DP21-0299 and although it appears the building plans match the DP in regard to building size and height until DP21-0299 is approved Zoning cannot approve the building plans. 2. The DP sheets provided in the building set either need to be the stamped approved DP set, marked for reference only or removed from the plans. 3. Sheet A110 references “DVPMT DESIGNATOR: 28 (LUC 3232)” & “FAR: 0.35*721,152=252,403 SF ALLOWED”, remove these references from the plan as they are no longer applicable. The LUC was replaced by the UDC in 2011. 4. Sheet A110 & A111 do not match DP21-0299 coordinate with Cypress Civil and ensure that the plans match or are removed from the plan set. 5. Sheet A301 shows a maximum wall height of 24’ and the DP shows 21’ clarify which is correct. If you have any questions about this transmittal, please contact Elisa Hamblin at Elisa.Hamblin@tucsonaz.gov. |
| 02/02/2022 | SBLOOD1 | ENGINEERING | REVIEW | Reqs Change | The DP needs to be approved before the building plans can be approved. Stephen Blood (520) 837-4958 Stephen.blood@tucsonaz.gov |
| 12/15/2021 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Approved | |
| 12/16/2021 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Completed | |
| 12/16/2021 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Reqs Change | Provide heating and cooling load calculations to justify the heating/cooling capacities of the specified HVAC units. Reference: Section C403.1.1 and C403.3.1, IECC 2018. |
| 12/16/2021 | ROBERT SHERRY | WATER | REVIEW | Completed | |
| 12/17/2021 | DAN SANTA CRUZ | ELECTRICAL-COMMERCIAL | REVIEW | Reqs Change | Lighting Comcheck not included on plan sheey E001 as stated per the 'Index Of Drawings plan sheet A100. |
| 12/29/2021 | JPEELDA1 | FIRE | REVIEW | Reqs Change | Sheet A101 shows that the FDC is located on the side of the building. FDC shall be located on the street side per IFC 2018, Section 912. Sheet A101 shows that the building will have a Stanpipe per Section 905, please remove from drawings as the building does not require standpipe systems. Sheet A101 shows fire alarm system per Section 907 for Group A but at a minimum the building will require a dedicated function fire alarm for waterflow and supervisory system of the NFPA 13 system per IFC 903.4 Questions: Jennifer Peel-Davis Jennifer Peel-Davis@Tucsonaz.gov 520-837-7033 |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 02/02/2022 | VVERA1 | OUT TO CUSTOMER | Completed |