Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Number: T21CM08633
Parcel: 13803031T

Review Status: Completed

Review Details: COMMERCIAL - BLDG/FIRE/ZONING/ENG

Permit Number - T21CM08633
Review Name: COMMERCIAL - BLDG/FIRE/ZONING/ENG
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
02/10/2022 LSHAMIS1 COMMERCIAL IMPACT FEE COMMERCIAL IMPACT FEE PROCESSING Completed
11/12/2021 GPENNIN1 ZONING REVIEW Approved
11/17/2021 SAFEBUILT 2ND PARTY REVIEW REVIEW Reqs Change Activity Number: T21CM08633


GENERAL:
Provide written responses to all review comments.
Provide a complete plan set.
Provide additional documents as requested by review staff.


STRUCTURAL REVIEW COMMENTS:
Denied
1. Provide Roof Framing Plan showing support to the 5 AC units AC-1 thru AC-5 on existing roof weighing 1400 pounds each and one of them 1850 pounds. Also supporting Energy Recovery Ventilators ERV-1 thru ERV-5 weighing 800 pounds each and one of them weighing 990 pounds.
2. The existing roof seems to be Steel Joists, provide info regarding steel joists reinforcing if the loading is off panel points of the steel joists.
3. Provide Structural Calculations showing the adequacy of the Roof Structure for the additional loads.
4. All Structural Calculations shall be sealed and signed by Professional Engineer registered in State of Arizona


BUILDING REVIEW COMMENTS:
Approved


MECHANICAL REVIEW COMMENTS:
Denied
1. Appliance shall be located a minimum of 10' from edge of roof (IMC2018,304.11)
2. Ducts installed on the roof shall be protected against the weather elements by weatherproof covering (IMC2018,603.16)
3. see narratives for marked up plans


ELECTRICAL REVIEW COMMENTS
Denied
E1.1 ELECTRICAL PLAN: Need to provide short circuit/fault current values at the new panels to prove that the KAIC ratings of the selected panels is acceptable per City of Tucson requirements.
E2.1 ELECTRICAL LIGHTING PLAN:
Need to provide Comcheck for interior lighting.
Need to identify lighting fixtures, typically with a lighting schedule.
E3.1 ELECTRICAL POWER and COMMUNICATIONS PLAN: Need to provide disconnect for primary side of transformers TA, TB, and TC that are within sight of the transformers per NEC 450.14.
E3.2 ELECTRICAL ROOF POWER PLAN: No electrical issues
E4.1 ELECTRICAL FIRE ALARM PLAN: Need to identify the Hexagon P symbol.
E5.1 PANEL SCHEDULES/LOAD CALCULATIONS/IECC COMPLIANCE: No electrical issues


PLUMBING REVIEW COMMENTS:
Denied
1). Trap primer detail #205 on Plan pg. P3 needs to include a shut off valve. - IPC 606.2 #3
2). P-1 lavatory on fixture schedule on plan pg. P3 needs to include an ASSE 1070 mixing valve -IPC 419.5
3). Add fixture spacing measurements for all restroom fixtures to detail "A" on plan pg. A4. -IPC 404.2 405.3.1
4). Provide combustion air illustrations & information for gas Water heater room. -IFGC 304.1
5). Detail #201 on plan pg. P3 states see mechanical plans for gas water heater flue continuation. ( not shown) please add this illustration. -IFGC 503.1
6). Add a demo/existing plan page to the plan set. IPC/IFGC A106.3.1.
11/23/2021 ROBERT SHERRY WATER REVIEW Completed
11/24/2021 LOREN MAKUS ENGINEERING REVIEW Passed
12/06/2021 JPEELDA1 FIRE REVIEW Approved

Final Status

Task End Date Reviewer's Name Type of Review Description
02/10/2022 NGARCIA3 OUT TO CUSTOMER Completed