Permit Review Detail
Review Status: Completed
Review Details: RESUBMITTAL
Permit Number - T21CM08577
Review Name: RESUBMITTAL
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 03/29/2022 | PAUL CAMARENA | ZONING | REVIEW | Reqs Change | FROM: Paul Camarena PDSD Zoning Review Section PROJECT: T21CM08577, T21CM08578, T21CM08579, T21CM08580, T21CM08581, T21CM08582, T21CM08583, T21CM08584, T21CM08585 Multi-Family (2nd Review) 4267 N 4TH AV Zoning R-2 TRANSMITTAL DATE: ?March ?29, ?2022 This site is located in the R-2 zone (UDC 4.7.9). A multi-family is a permitted use in this zone (Table 4.8-2). See Use-Specific Standards 4.9.7.B.6, .9, & .10. These comment are still applicable. 1. Zoning has reviewed the building plans for compliance with DP21-0216 and although it appears that the buildings matches what is shown on the DP, until the DP is approved Zoning cannot approve the building plans. 2. Ensure that all site details match what has been submitted on the DP. If you have any questions about this transmittal, Contact Paul Camarena at (520)837-4986 or by email Paul.Camarena@tucsonaz.gov |
| 04/06/2022 | SAFEBUILT | 2ND PARTY REVIEW | REVIEW | Reqs Change | Activity Number: T21CM08577, T21CM08578, T21CM08579, T21CM08580, T21CM08581, T21CM08582, T21CM08583, T21CM08584, T21CM08585 GENERAL: Provide written responses to all review comments. Provide a complete plan set. Provide additional documents as requested by review staff. STRUCTURAL REVIEW COMMENTS: Conditionally Approved 1. The response to the structural correction items indicate that the Geotechnical Report will be submitted and it was not submitted in this submittal. The Inspector to verify info provided on Sheet S0.0 and the Structural Calculations matches with the Geotechnical Report. BUILDING REVIEW COMMENTS: Approved MECHANICAL REVIEW COMMENTS: Conditionally Approved 1. Applicant shas stated in his response that there is no pool or pool equipment room on this project to review. 2. Approved/Subject to field approval ELECTRICAL REVIEW COMMENTS Conditionally Approved PLUMBING REVIEW COMMENTS: Denied Second Review: 1). SAME-Plan page A5.01 only shows 10.5 to 12" from sidewall to lavatory center. The minimum requirement is 15" See details #15 & #22 -IPC 405.3.1 2). SAME-Supply the site/civil site utility piping plan to see that the Building water & sewer stub outs correlate with the continuation of the water service & sewer. -IPC 106.3.1 SEE P0.1 4-7 OK 8). Per response Sheet Fire System permitted Separately. If you require additional clarification regarding these comments, please contact Doris Benoit at doris.benoit@tucsonaz.gov |
| 04/15/2022 | IMONSHI1 | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Reqs Change | |
| 05/09/2022 | SBLOOD1 | ENGINEERING | REVIEW | Approved |