Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - BLDG/FIRE/ZONING/ENG
Permit Number - T21CM07976
Review Name: COMMERCIAL - BLDG/FIRE/ZONING/ENG
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
10/22/2021 | SAFEBUILT | 2ND PARTY REVIEW | REVIEW | Reqs Change | Activity Number: T21CM07976 GENERAL: Provide written responses to all review comments. Provide a complete plan set. Provide additional documents as requested by review staff. STRUCTURAL REVIEW COMMENTS: Denied 1. Refer Detail 8/S521 and 9/S521. Untreated Lumber is called out for 6X6 Douglas-Fir #2. Verify and make revision as needed. 2. Refer Detail 11/S521. C6x8.2 is used. Verify if C6 need to be galvanized since it’s exposed to weather. BUILDING REVIEW COMMENTS: Denied 1. Sheet A021: The occupant load factors used for the business areas in the occupant load analysis are incorrect. Please correct and recalculate. MECHANICAL REVIEW COMMENTS: Conditionally Approved Approved/subject to field approval ELECTRICAL REVIEW COMMENTS Conditionally Approved E961 INTRUSION SYSTEM FRONT AREA PLAN: Could not locate Notes 2, 3, 4, and 13. PLUMBING REVIEW COMMENTS: Denied 1). Notate on plan page P601 the manufacturer name and model number of the wall hung electric water cooler. -IPC A103.6.1 2). Plan page P601 states refer to architectural plans for wall hung electric water cooler mounting height, plan set does not show those heights, please add. -IPC 410.3 3). Lactation room sink on P601 needs tempered water. -IPC 607.1, 607.1.2 4). Add mixing valve manufacturer name & model number of the mixing valve shown on P601 detail #4. IPC A106.3.1 5). Beverage equipment backflows notated on P601 need to include the types & listing standards. ( spec sheets not included as noted) -IPC 608.17.1.2 6). Notate on P601 that the espresso & beverage sink waste will discharge indirectly to a floor sink that is connected to the grease system. -IPC 1003.3 Tucson Amendment |
10/27/2021 | SSHIELD1 | ENGINEERING | REVIEW | Passed | |
10/27/2021 | ROBERT SHERRY | WATER | REVIEW | Completed | |
10/27/2021 | STEVE SHIELDS | ZONING | REVIEW | Approved | |
10/27/2021 | SSHIELD1 | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Passed | |
11/16/2021 | JPEELDA1 | FIRE | REVIEW | Approved |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
11/16/2021 | VVERA1 | OUT TO CUSTOMER | Completed |