Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Completed
Review Details: OTHER
Permit Number - T21CM04863
Review Name: OTHER
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
06/29/2021 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Approved | |
07/08/2021 | DAN SANTA CRUZ | ELECTRICAL-COMMERCIAL | REVIEW | Reqs Change | Please address the following electrical plan review comments. Also provide a written response. Is the new switchgear replacement like for like? If yes, please indicate this on the plans. If not, provide a complete line diagram including old and new equipment and grounding details, OCPD’s, GFI protection, Voltage, Phase, Amps, AIC, etc. Indicate on the plan if there is any change in load. If yes, provide complete load calculations. Identify the old and new switchgear on the electrical floorplan. Identify the temporary 500kw generator on the electrical floorplan as mentioned in the CONSTUCTION PHASING notes and provide more details for the temporary conductors, grounding and terminations. Where is generator #1? Is this a new generator on the new generator pad per KEYNOTE #6. Provide detailed information for the new generator (Ratings), feeders, OCPD’s , voltage, phase, etc. Provide information addressing any changes for the Generator and Switchgear grounding . Ref; 2018 IBC sec 107.2.1, 2017 NEC, City of Tucson Commercial Permit/Plan Submittal Requirements. |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
07/09/2021 | NGARCIA3 | OUT TO CUSTOMER | Completed |