Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - TI
Permit Number - T21CM04619
Review Name: COMMERCIAL - TI
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 06/17/2021 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Approved | |
| 06/24/2021 | DAN SANTA CRUZ | ELECTRICAL-COMMERCIAL | REVIEW | Reqs Change | Please address the following electrical plan review comments. Also provide a written response. Ref; Plan Sheet EL1.1, Line Diagram. Provide more detail as to how you plan to utilize a supply side tap into a 4000 amp switchgear bus for a 20 amp lighting branch circuit. Is an additional tap besides the PV interconnection? Provide a Code compliant method. Include conduit, conductor, disconnecting means, overcurrent protection, etc. Ref; 2018 IBC sec 107.2.1, 2017 NEC, 2012 Tucson/Pima County Outdoor Lighting Code (OLC), City of Tucson Commercial Plan Submittal Requirements |
| 07/08/2021 | SSHIELD1 | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Passed | |
| 07/08/2021 | STEVE SHIELDS | ZONING | REVIEW | Approved | |
| 07/08/2021 | SSHIELD1 | ENGINEERING | REVIEW | Passed |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 07/12/2021 | DBENOIT1 | APPROVAL SHELF | Completed |
| 07/12/2021 | DBENOIT1 | OUT TO CUSTOMER | Completed |
| 07/12/2021 | DBENOIT1 | REJECT SHELF | Completed |