Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - TI
Permit Number - T21CM03396
Review Name: COMMERCIAL - TI
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 05/03/2021 | ROBERT SHERRY | WATER | REVIEW | Completed | |
| 05/17/2021 | SAFEBUILT | 2ND PARTY REVIEW | REVIEW | Reqs Change | Activity Number: T21CM03396 GENERAL: o Provide written responses to all review comments. o Provide a complete plan set. o Provide additional documents as requested by review staff. STRUCTURAL REVIEW COMMENTS: Denied 1. Details 20 and 21 shown on Drawing S1.5 are not marked anywhere on the Floor Plans. Remove these if they are not used. 2. Roof drainage and secondary drains are to comply with IBC 1502.1. 3. Refer Drg. S1.0. Loads: Ultimate wind speed is correctly called as 115 mph. Design wind speed (Vasd) is called 85 mph. Verify and make corrections as needed. BUILDING REVIEW COMMENTS: Denied 1. A separation between R-2 and S-2 is required. The fire barriers on the east side of the building will need to be upgraded. 2. No structural review completed. ELECTRICAL REVIEW COMMENTS Denied Why wasn't this permitted with the Evidentiary Vehicle Storage application? E2.1 MECHANICAL POWER PLAN: No Electrical issues. New SES panel schedule shown in two locations, on E2.1 and E4.0 E4.0 ONE LINE DIAGRAM, PANEL SCHEDULES AND CALCULATION: Panel L1 shown in SES Panel with 200-amp CB, yet shown on Riser as 100-amp MCB panel. Typically, a 100-amp MCB panel cannot accept 4/0 conductor. Correct or clarify. Note for Panels A and H not clear. Potentially??? Call out as existing. If there is a high probability of a hazardous code violation or abuse of NEC tap rules, design to correct. Where does existing panel P1 get power from? Subpanel of panel P? MECHANICAL REVIEW COMMENTS: Conditionally Approved NOTE: Every effort has been made to identify code violations. Any oversight by the reviewer shall not be considered as authority to violate, set aside, cancel or alter applicable codes or ordinances. The plan review and permit issuance shall not be considered a warranty or guarantee. The designer is responsible for following all applicable federal, state, and municipal codes and ordinances. PLUMBING REVIEW COMMENTS: Denied ADD new section 412.11 to read: 412.11 Automatic faucets. New or replacement faucets serving lavatories in all buildings other than R3 occupancies, individual units in R2 occupancies, or International Residential Code structures shall be provided with automatic faucets in accordance with 419.6. ADD new section 419.6 to read: 419.6 Automatic faucets. Lavatories installed in all buildings other than R3 occupancies, individual units of R2 occupancies, or International Residential Code structures shall be provided with automatic faucets dispensing a maximum of 0.25 gallon per metering cycle. Demonstrate compliance. |
| 05/18/2021 | JPEELDA1 | FIRE | REVIEW | Reqs Change | test |
| 05/18/2021 | SSHIELD1 | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Passed | |
| 05/18/2021 | STEVE SHIELDS | ZONING | REVIEW | Reqs Change | PDSD TRANSMITTAL FROM: PDSD Zoning Review PROJECT: T21CM03396 4902 E Pima St Addition and remodel to existing Fire Station (1st Review) TRANSMITTAL DATE: May 18, 2021 This site is located in the R-1 zone (UDC 4.7.8). Protective Service (government owned and operated only) is a permitted use in this zone (Table 4.8-2) subject to Use Specific Standard 4.9.13.F. 1. The building plans have been reviewed for compliance with DP20-0222 and although it appears that the building plans match the DP until the DP is approved Zoning cannot approve the building plans. If you have any questions about this transmittal, please contact Elisa Hamblin or Elisa.Hamblin@tucsonaz.gov. |
| 05/18/2021 | JPEELDA1 | FIRE | REVIEW | Reqs Change | Code Summary Under Fire Protection: remove the fire sprinkler notes if not fire sprinklering Jennifer.Peel-Davis@Tucsonaz.gov 520-837-7033 |
| 05/27/2021 | SBLOOD1 | ENGINEERING | REVIEW | Reqs Change | Engineering has reviewed the building plans for compliance with DP20-0222 and although the building plans appear to match the DP until the DP is approved Engineering cannot approve the building plans. Stephen Blood (520) 837-4958 Stephen.blood@tucsonaz.gov |