Permit Number: T21CM02892
Parcel: 10511061R

Review Status: Completed

Review Details: COMMERCIAL - TI

Permit Number - T21CM02892
Review Name: COMMERCIAL - TI
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
04/13/2021 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Passed
04/13/2021 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Completed
04/13/2021 ROBERT SHERRY WATER REVIEW Completed
04/14/2021 JPEELDA1 FIRE REVIEW Approved
04/20/2021 ERIC NEWCOMB COMMERCIAL IMPACT FEE COMMERCIAL IMPACT FEE PROCESSING Passed
04/20/2021 ERIC NEWCOMB BUILDING-COMMERCIAL REVIEW Reqs Change 1. Sheet A000; Building Codes: Please replace the 2010 ADA Standards with the 2009 ICC/ANSI A117.1.
2. Sheet A001; ADA Seating Requirements: The minimum clearance at ADA tables references 10/A500. Please revise that reference.
3. Sheet A200; Floor Plan Legend: The new wall indicates 'new 2x4 stud wall'. Please revise that note for metal studs.
4. Sheet A500; Detail 1: The title indicates 3 5/8" Stud Partition, but the stud note indicates 6" 20 gauge metal studs. Please coordinate.
5. Sheet A500; Detail 3: The structural member at the top of the operable wall panel indicates 'Structural Member not by Panel Fold'. Please provide a structural calculation for that member, and indicate the member size on a detail, including member bracing as required.
6. General: Please provide written responses to all review comments.
04/27/2021 DAN SANTA CRUZ ELECTRICAL-COMMERCIAL REVIEW Reqs Change Please address the following electrical plan review comments. Also provide a written response.

Designate branch circuit numbers and panel for all power and lighting, and any other electrical devices or equipment on the electrical plans. NEC 408.4.

Show all new or relocated luminaires on the power and or lighting plans.

Show the location of the Loadcenter or Panel on the electrical plan.

Provide a complete panel schedule including load calculations for added electrical loads.

Provide a complete luminaire schedule if new lighting is proposed. If new lighting is proposed, provide 2018 IECC compliance.

Ref; 2018 IBC sec 107.2.1, 2017 NEC, 2018 IECC.
04/28/2021 PCAMARE1 ENGINEERING REVIEW Passed
05/03/2021 STEVE SHIELDS ZONING REVIEW Approved