Permit Review Detail
Review Status: Completed
Review Details: RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO
Permit Number - T21CM02417
Review Name: RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 03/18/2021 | SBLOOD1 | ENGINEERING | REVIEW | Approved | |
| 03/25/2021 | KEN VAN KARSEN | BUILDING-RESIDENTIAL | REVIEW | Reqs Change | T21CM02417 PLAN REVIEW COMMENTS Plan review for the above referenced structure has been completed. This letter reflects comments to be addressed. In order to facilitate a shorter back check time, please provide two sets of updated plans and calculations with a written response to each of the notated items indicating action taken. Do not cloud the changes made for comment revisions. SCOPE OF REVIEW: The scope of this plan review covers architectural, plumbing, mechanical, energy conservation and electrical. All code references are to the 2018 International Residential Code and 2018 International Energy Conservation Code. All features were checked only to the extent allowed by the submittals provided. All portions of this project are assumed to meet or will meet other departmental requirements, conditions and concerns before permit approval. GENERAL REQUIREMENTS: A new dwelling unit (includes a kitchen) requires collection of development impact fee when the building permit is processed, City of Tucson Ordinance #11203. GENERAL COMMENTS: 1. A dwelling unit providing complete independent living facilities requires compliance with design ordinances for handicap, solar water, photo-voltaic and gray water preparations. Design Ordinances adopted by the City of Tucson. 2. Show compliance with the Inclusive Home Design Ordinance adopted by the City of Tucson Ordinance #10463 on 10/16/2007. Notate accessible route, minimum door width, changes in floor elevation, door hardware, electrical outlet reach range, grab bar reinforcement, etc. 3. All SFR and Duplex plans submitted after March 1, 2009 require a solar water system, or future installation preparation City of Tucson Ordinance #10549 with one of the following provisions: ½”control conduit and two ¾” copper piping for water with rooftop termination; straight 3” capped sleeve; or an accessible attic (clear path 30” wide x 30” high) over the water heater. Show appropriate notation. 4. All SFR and Duplex plans submitted after July 1, 2009 require a solar photo-voltaic system, or future installation preparation City of Tucson Ordinance #10549 . a. Show a minimum 300 SF clear solar-ready zone on a roof or framing plan, T103.3. Model plans should show four typical south facing roof surfaces. b. Label a double breaker space for future Photo Voltaic on the panel schedule opposite end from the main/supply side, T103.9. 5. All construction drawings submitted after June 1, 2010 for one- or two-family dwellings must provide gray water utilization or preparation, Ordinance #10579/11089 revised July 9, 2013. Include two clothes washer standpipes at an exterior wall, one with an above grade stub-out, and one plumbed to the building drain. FLOOR PLANS: 1. Show a maximum ½” floor elevation changes at a notated accessible route entrance on the floor plan, R106.1.1. MECHANICAL PLANS: 1. Provide (an HVAC system with fresh air intake) whole-house mechanical ventilation, or controlled exhaust with a calculated airflow rate, R303.4; N1103.6 & M1505.4. Show the system and appropriate flow rate setting on the plans. A one bedroom dwelling less than 1500 SF requires a 30 CFM continuous setting. INTERNATIONAL ENERGY CONSERVATION CODE: 1. Show the installation of wall insulation between the dwelling and vented utility room, N1102.1. 2. Energy Certificate: (Mandatory) place near the indoor furnace or in utility room, N1101.14. Add notation to plans. Please contact the plans reviewer if you have any questions: Ken Van Karsen (520) 837-4912 PDSD-Residential@tucsonaz.gov City of Tucson Residential Plan Review |
| 04/08/2021 | STEVE SHIELDS | ZONING | REVIEW | Approved | |
| 04/08/2021 | SSHIELD1 | NPPO | REVIEW | Passed |