Permit Number: T21CM02174
Parcel: 137055460

Review Status: Completed

Review Details: COMMERCIAL - TI

Permit Number - T21CM02174
Review Name: COMMERCIAL - TI
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
03/11/2021 DTRAMME1 ENGINEERING REVIEW Passed
03/15/2021 JPEELDA1 FIRE REVIEW Approved
03/25/2021 ERIC NEWCOMB COMMERCIAL IMPACT FEE COMMERCIAL IMPACT FEE PROCESSING Passed
03/25/2021 ERIC NEWCOMB BUILDING-COMMERCIAL REVIEW Approved
03/30/2021 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Reqs Change 1. Revise the sequence of operation for the restroom exhaust fan so that all of the air supplied to the restrooms will be exhausted (i.e. all of the air supplied to each restroom is to be exhausted during the hours of operation even if the lights are off). The exhausted air from the restrooms shall be limited to no more than 10% of any subsequent supply air stream. Reference: Section 403.2.1 (4), IMC 2018.
2. Nail salons require a source-capture exhaust system for each manicure and pedicure station. The exhaust inlets shall b located a maximum of 12” horizontally and 12” vertically from the point of chemical application. Provide a detail showing how this is to be accomplished. Reference: Table 403.3.1.1, footnote h and Section 502.20, IMC 2018.
03/30/2021 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Reqs Change 1. Provide a metering faucet for the lavatory, dispensing a maximum of 0.25 gallons per metering cycle. Verify that the faucet cycle will last for at least 10-seconds. Reference: Section 419.6, IPC 2018, as amended by the City of Tucson and Section 606.4, ICC/ANSI A117.1-09.
2. Provide a detail of the water heater installation, including the excess pressure relief, expansion tank, vacuum relief or other anti-siphon device, safety pan, and valves. Reference: Sections 503.1, 504, 606.1, 607.2, and 607.3, IPC 2018.
3. Revise the hot water distribution system to ensure that the distance from the hot water source to the hot water termination for the public lavatory complies with the requirements of Section C404.5, IECC 2018.
4. Specify the type of backflow prevention device to be installed for each pedicure chair water connection. Reference: Sections 608.1 and 608.3, IPC 2018 and https://www.tucsonaz.gov/files/pdsd/codes-ordinances/FootSpa_Plumbing.pdf.
03/30/2021 ROBERT SHERRY WATER REVIEW Reqs Change Show the location of the water meter, backflow preventer, and the water service pipe on a site plan. Provide the total water demand that will be served by the water meter. Reference: Section 107.2.1 and 107.2.6, IBC 2018.
04/07/2021 DAN SANTA CRUZ ELECTRICAL-COMMERCIAL REVIEW Approved
04/09/2021 STEVE SHIELDS ZONING REVIEW Approved