Permit Number: T21CM00864
Parcel: 132130770

Review Status: Completed

Review Details: COMMERCIAL - NEW

Permit Number - T21CM00864
Review Name: COMMERCIAL - NEW
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
02/23/2021 JPEELDA1 FIRE REVIEW Approved
02/23/2021 ROBERT SHERRY WATER REVIEW Completed
02/24/2021 STEVE SHIELDS ZONING REVIEW Reqs Change ZONING REVIEW TRANSMITTAL

FROM: PDSD Zoning Review

PROJECT:
T21CM00864
1725 E Tucson Marketplace Bl
Travelers Accommodation

TRANSMITTAL: February 24, 2021
This site is located in PAD-15. Travelers Accommodation is a permitted use in this zone.

1. Zoning has reviewed the building plans but cannot approve DP20-0240 is approved.

2. Provide a copy of the approved Design Review letter, see PAD-15 Section C.6, with your next submittal.

If you have any questions about this transmittal, please contact Elisa Hamblin at Elisa.Hamblin@tucsonaz.gov
03/16/2021 LSHAMIS1 COMMERCIAL IMPACT FEE COMMERCIAL IMPACT FEE PROCESSING Completed
03/16/2021 SAFEBUILT 2ND PARTY REVIEW REVIEW Reqs Change STRUCTURAL:
Mustafa Cankat - Denied

Reason:
Date Completed : 3/15/2021

SPRINGHILL SUITES TUCSON, AZ SSM001.102421 Structural Comments Mustafa Cankat PE 03/15/2021
1) General Structural Notes: Please compare the seismic data in these notes with the data listed in Geotechnical report. Verify.
2) List of the load combinations are used in the design and identify any design software used in lateral framing analysis.
3) Provide summary of cumulative drifts from wind and seismic forces for the 4-story building. Demonstrate that maximum story drift under seismic forces ASCE 7-16 section 12.12 or serviceability limit of H/400 under wind load is not exceeded.
4) Provide information on the framing plans about floor and roof diaphragm shears, collectors and drag forces.
5) Provide C&C wind design pressures for windows and doors.
6) Provide C&C wind design uplifts for roofing attachment based on zones and tributary area of 10 sq.ft. List also C&C roof uplift pressures for roof trusses based on their tributary area.
7) S2.0: Keynote # 4 refers shaded areas. Please show on plan with the extend of the area with mild steel.
8) S2.1: Provide a loading criteria or post on the foundation plan the total uniform loads from wood stud shear walls and concentrated loads from the post columns where they have no additional footing. See specifically corridor areas on grids 12 thru 21.
9) S2.2: See B9 steel beam on grid line E spanning between grids 9.5 & 10.6. Did you considered the concentrated load from another B9 beam which frames into it at grid 10.
10) S2.2: Please identify the columns starts at 2nd level.
11) S2.2: SW1, SW2 and SW3 appears to start at 2nd level. Explain briefly how the shear wall base reactions from these shear walls are transferred to foundation. (Load path)
12) S2.1: See column C5 next to grid H. Locate this column dimensionally from grid 4.
13) S3.0: Detail 115; specify embedment length of ¾ “dia. Expansion bolt and provide a note that bolts shall miss the PT tendons.
14) From serviceability and performance perspective, the most significant potential problem issue related to multi-story wood frame construction is wood shrinkage. Provide shrinkage estimation calculation.
15) Please respond in writing and provide brief narrative for the revisions are made.



BUILDING:
Scott Davis Denied

Reason:
Date Completed : 3/12/2021 9:38:56 PM
1. Submit a copy of the City of Tucson approved site plan per city code of ordinances.
2. Submit entire building envelope COMcheck energy code certificate per 2018 IEC C402.
3. Submit construction safeguards during construction locations and details per 2018 IBC 3302.
4. Provide main entrance handicap accessibility route and construction details per 2018 IBC 1102.
5. Show handicap parking and ramp construction details and specifications per 2018 IBC 1102.
6. Provide swimming pool and spa locations on site plan and specifications per 2018 IBC 107.3.
7. Show elevator shaft enclosure fire resistance location and construction details per 2018 IBC 713.
8. Provide exterior masonry screen walls and columns foot sizes and details per 2018 IBC 1807.
9. Show interior finishes flame spread and smoke development information per 2018 IBC 803.
10. Provide non-load bearing wall with diagonal wall brace spacing information per 2018 IBC 107.3.
11. Show emergency panic hardware at all interior egress stairway doors per 2018 IBC 1010.
12. Provide stairways risers, handrails and guardrails heights and dimensions per 2018 IBC 1011.


ELECTRICAL:
Ron Ross - Denied

Reason:
Date Completed : 3/7/2021 Springhill Suites Review
By: Ron Ross PE March 7, 2021 Electrical comments:
1) E001 ELECTRICAL NOTES, SYMBOLS, ABBREVIATIONS: No Electrical comments.
2) ES101 ELECTRICAL SITE PLAN: No Electrical comments.
3) EL101 1ST FLOOR - LIGHTING FLOOR PLAN: No Electrical comments.
4) EL102 2ND FLOOR - LIGHTING FLOOR PLAN: No Electrical comments.
5) EL103 3RD FLOOR - LIGHTING FLOOR PLAN: No Electrical comments.
6) EL104 4TH FLOOR - LIGHTING FLOOR PLAN: No Electrical comments.
7) EM201 1ST FLOOR - ELECTRICAL MECHANICAL FLOOR PLAN: No Electrical comments.
8) EM202 2ND FLOOR - ELECTRICAL MECHANICAL FLOOR PLAN: IDF West Room #2017 missing Panel 2LV6. 9) EM203 3RD FLOOR - ELECTRICAL MECHANICAL FLOOR PLAN: No Electrical comments.
10) EM204 4TH FLOOR - ELECTRICAL MECHANICAL FLOOR PLAN: IDF West Room #4016 missing Panel 4LV6. Electrical room Panel 4LV7 should match location on Sheet EP104.
11) EM205 ROOF ELECTRICAL MECHANICAL FLOOR PLAN: No Electrical comments.
12) EP101 1ST FLOOR - ELECTRICAL FLOOR PLAN: Confirm that Distribution Section 1LVDP1 complies with NEC 110.26 clearance requirements. Door swings into working area.
13) EP102 2ND FLOOR - ELECTRICAL FLOOR PLAN: No Electrical comments. EP103 3RD FLOOR - ELECTRICAL FLOOR PLAN: No Electrical comments.
14) EP104 4TH FLOOR - ELECTRICAL FLOOR PLAN: NEC 110.26 issue from Door swing into IDF room #4016 for panel 4LV8.
15) EP105 ROOF ELECTRICAL FLOOR PLAN: No Electrical comments.
16) EP401 ENLARGED SUITE ELECTRICAL PLANS: No Electrical comments.
17) EP402 ENLARGED PLANS: Pool panel in Pool equipment room 010 not shown.
18) EP601 PANEL SCHEDULE: No Electrical comments.
19) EP602 PANEL SCHEDULE: Panel 1LV4 could use #7, a 200 amp feeder vs #13, a 250 amp feeder.
20) EP603 PANEL SCHEDULE: Panels 2LV4 & 2LV5 could use #4, a 200 amp feeder vs #13, a 250 amp IG feeder.
21) EP604 PANEL SCHEDULE: No Electrical comments.
22) EP605 PANEL SCHEDULE: No Electrical comments.
23) EP606 PANEL SCHEDULE: Panels 3LV4 & 3LV5 could use #4, a 200 amp feeder vs #13, a 250 amp IG feeder.
24) EP607 PANEL SCHEDULE : No Electrical comments.
25) EP608 PANEL SCHEDULE: Panels 4LV4 & 4LV5 could use #4, a 200 amp feeder vs #13, a 250 amp IG feeder.
26) EP609 PANEL SCHEDULE: No Electrical comments.
27) EP701 ELECTRICAL SINGLE LINE DIAGRAM AND FIRE RISER DIAGRAM:
a. Sheet name needs to be updated on Electrical sheet legend.
b. Panel 1LV4 could use #7, a 200 amp feeder vs #13, a 250 amp feeder.
c. Panels 2LV4 & 2LV5 could use #4, a 200 amp feeder vs #13, a 250 amp IG feeder.
d. Panels 3LV4 & 3LV5 could use #4, a 200 amp feeder vs #13, a 250 amp IG feeder.
e. Panels 4LV4 & 4LV5 could use #4, a 200 amp feeder vs #13, a 250 amp IG feeder.
28) EP702 LOAD CALCULATION SHORT CIRCUIT CALCULATION: Sheet name needs updated/added in electrical sheet legend.
29) EP703 LIGHTING CONTROL DIAGRAMS: Sheet name needs to be added in electrical sheet legend.
30) EY101 1ST FLOOR PLAN - SPECIAL SYSTEMS FLOOR PLAN: Do not see Fire Alarm Pull stations at egress doors on first floor.
31) EY102 2ND FLOOR PLAN - SPECIAL SYSTEMS FLOOR PLAN: No Electrical comments.
32) EY102 2ND FLOOR PLAN - SPECIAL SYSTEMS FLOOR PLAN: No Electrical comments.
33) EY103 3RD FLOOR PLAN - SPECIAL SYSTEMS FLOOR PLAN: No Electrical comments.
34) EY104 4TH FLOOR PLAN - SPECIAL SYSTEMS FLOOR PLAN: No Electrical comments.
35) EY701 FIRE ALARM RISER DIAGRAM, COMMUNICATION CONDUIT RISER DIAGRAM: No Electrical comments.



MECHANICAL:
Elizabeth Prida - Denied

Reason:
Date Completed : 3/11/2021
Springhill Suites By Marriott

Project submittal (SSM001.022421) T21CM00864 Mechanical
Review Status-Rejected

Mechanical comments
1. Note on plans 10’ minimum distance shall be provided between intake and exhaust discharge. IMC-501.3.1
2. Pride fire damper and/or smoke damper at fire rated walls or smoke barriers are penetrated by ducts, specifically at ground floor. Also, provide installation detail. IMC-(B) 607.5
3. Provide access panel for all inline fans installed above ceiling. IMC-306.1 4. Provide Energy Calculations as per IECC-C401.2
5. Provide detail to show how Condensing Units and H/P will be attached to building structure to support wind and seismic load. IMC-301.18 and 301.15

Elizabeth Prida, PE




PLUMBING:
Elizabeth Prida
Review Status-Rejected
1. Provide a lint interceptor for clothes washers’ discharge. Show interceptor on floor plans-Plumbing and isometrics. Also, revise Plumbing Fixture schedule and vent the interceptor as required. IPC-1003.6
2. Provide Energy Calculations, as per IECC-C401.2


Elizabeth Prida, PE
03/17/2021 LOREN MAKUS ENGINEERING REVIEW Reqs Change 1. The development package must be approved first.
2. Ensure the roof drainage matches the approved development package.

Final Status

Task End Date Reviewer's Name Type of Review Description
03/18/2021 IMONSHI1 OUT TO CUSTOMER Completed