Plan Number: T20PRE0180
Parcel: Unknown

Review Status: Completed

Review Details: PREAPPLICATION LABELS

Plan Number - T20PRE0180
Review Name: PREAPPLICATION LABELS
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
12/03/2020 ANDREW CONNOR LANDSCAPE REVIEW Completed Show compliance with landscaping and screening requirements by locations, material descriptions, and dimensions. Specific plant or hardscape material shall be detailed on a landscape plan. A detailed landscape plan is required. In accordance with Section 2-10.0.0, Landscape Plan Requirements.
12/16/2020 ZELIN CANCHOLA COT NON-DSD TRAFFIC Completed No adverse comments. Standard requirements will apply for the development package.
12/17/2020 GDAURIA1 COT NON-DSD FIRE Completed
12/22/2020 ELISA HAMBLIN ZONING REVIEW Completed CDRC Thursday Pre-Submittal Transmittal
PDSD Zoning Review

FROM: Elisa Hamblin, AICP; Principal Planner

PROJECT: Thursday Pre-submittal meeting – T20PRE0180
Address: 975 E MacArthur Cl
Parcel(s): 132-16-6500
Zoning: I-1
Existing Use: Vacant
Proposed Use: Commercial – Medical Service, Outpatient

TRANSMITTAL DATE: December 21, 2020

COMMENTS:
1. Development must comply with the Administrative Manual Section 2-06 - Development Package.
2. The proposed development of the site is for a Medical Service, Outpatient use, which is permitted in the I-1 subject to use-specific standards 4.9.13.Q.
3. The proposal appears to meet development standards such as height, setbacks, parking, etc.
4. Bike parking is required in accordance with UDC Article 7.4.8. It appears two short-term and two long-term bike parking spaces will be required.
5. Pedestrian access (sidewalk/crosswalk) is required from each street that fronts the development site.
6. Any planned future development or phasing of this development site will require additional review.
7. The comments provided are preliminary and are not to be assumed as a complete review of the proposal. During the Development Package review process, a full review will be made by Zoning to assure compliance with the applicable UDC development criteria and Technical Standards.

If you have any questions please contact me at elisa.hamblin@tucsonaz.gov.
12/22/2020 SBEASLE1 TUCSON WATER NEW AREA DEVELOPMENT REVIEW Completed 200 - 230 pm - T20PRE0180 - 975 E MACARTHUR CI - Site I Smile Dentistry

1. There is an existing 8" cement asbestos (CA) water main (WO 5608) in Fair Street, and an existing 6" CA water main (WO 5532) in Park Avenue that can serve this proposed development.
2. These existing water mains are in two different pressure zones. The water pressure in the existing 6" CA water main (WO 5532) in Park Avenue is substantially higher.
3. The closest fire hydrant is located on the site. It is connected to the existing 8" cement asbestos (CA) water main (WO 5608) in Fair Street.
4. Any questions, comments or concerns about these projects may be directed to:

Tim Rowe, P.E., Civil Engineer
Tucson Water, New Development Section
310 W. Alameda St.
P.O. Box 27210
Tucson, AZ 85726-7210
(520) 837-2106
tim.rowe@tucsonaz.gov
12/22/2020 SBLOOD1 ENGINEERING REVIEW Completed 1. Site is within shallow sheet flow flood zone - Look at Desert Shadows Wash report or Provide new study to determine flood characteristics that might affect the site.
2. Balanced basin detention required: no increase for peak discharge for 2, 10, and 100-yr events.
3. 5-yr threshold retention is required.
4. Provide drainage report.
5. Maximize water harvesting.

Stephen Blood