Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Plan Number: T20PRE0137
Parcel: Unknown

Address:
847 E DREXEL RD

Review Status: Completed

Review Details: PREAPPLICATION

Plan Number - T20PRE0137
Review Name: PREAPPLICATION
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
10/12/2020 ANDREW CONNOR LANDSCAPE REVIEW Completed Show compliance with landscaping and screening requirements by locations, material descriptions, and dimensions. Specific plant or hardscape material shall be detailed on a landscape plan. A detailed landscape plan is required. In accordance with Section 2-10.0.0, Landscape Plan Requirements.
10/19/2020 ZELIN CANCHOLA COT NON-DSD TRAFFIC Completed No sdvere comments. Standard requirments will apply
10/20/2020 LOREN MAKUS ENGINEERING REVIEW Completed T20PRE0137
1. This site is within a critical basin. Critical basin detention and 5-year threshold retention is required. A drainage report is required.
2. Maximize water harvesting.
3. Centralized solid waste collection is required. (ES must approve individual collection for multifamily projects. This approval will require a TSMR.)
10/21/2020 GDAURIA1 COT NON-DSD FIRE Completed * Fire sprinklers required.
* No exterior portion of any structure to be more than 600' from a hydrant.
* Fire lane signs required on one side of the roadway,
* Fire access required to within 150' of any exterior portion of the units.
* Fire access roads exceeding 150' shall be provided with an approved turn around.
10/21/2020 ELISA HAMBLIN ZONING REVIEW Completed CDRC Thursday Pre-Submittal Transmittal
PDSD Zoning Review

FROM: Elisa Hamblin, AICP; Principal Planner

PROJECT: Thursday Pre-submittal meeting – T20PRE0137
Address: 847 and 855 E Drexel Rd
Parcel(s): 14019030A, 14019029A
Zoning: R-2
Existing Use: Vacant
Proposed Use: Multifamily Development

TRANSMITTAL DATE: October 21, 2020

COMMENTS:
1. Development must comply with the Administrative Manual Section 2-06 - Development Package.
2. The proposed use of Multifamily Development is permitted in the R-2 zone, subject to use-specific standards 4.9.7.B.6, .9, & .10.
3. Development standards such as density, height, and parking appear to be met.
4. Long-term bike parking is required at a ratio of 0.5 spaces per bedroom. With 84 bedrooms, a total of 42 spaces are required. Long-term bike parking can be provided within individual units, bike lockers or other means. See UDC Article 7.4.9.D.
5. Setbacks to the north, east and west are 10 ft or ¾ the wall height, whichever is greater. Setbacks need to be slightly larger as wall height is measured from design grade, not finished floor elevation.
6. Drexel Rd is a Major Street and Route. Setback on Drexel Rd is 21 ft or the wall height, whichever is greater, as measured from back of future curb. Drexel Rd appears to not be at full right-of-way width. Please verify future curb location with Department of Transportation and Mobility.
7. A lot combination processed with Pima County will be required.
8. The comments provided are preliminary and are not to be assumed as a complete review of the proposal. During the Development Package review process, a full review will be made by Zoning to assure compliance with the applicable UDC development criteria and Technical Standards.

If you have any questions please contact me at elisa.hamblin@tucsonaz.gov.
10/22/2020 SBEASLE1 TUCSON WATER NEW AREA DEVELOPMENT REVIEW Completed 130 - 200 pm - T20PRE0137 - SiteFlexible Lot Dev Colonia Mariposa, multi-family

1. There are no public water mains on this property, but a 6" PVC public water main (PN 135-1985 & FR 11739) terminates near the proposed cul-de-sac at the NW corner of the project.
2. New on-site public water mains will need to connect PN 135-1985 & FR 11739 to the 8" cement asbestos public water main (PN 061-1964) on the south side of Drexel Road.
3. The design of the new on-site public water mains will need to go through Tucson Water's Master Plan and Design Plan review processes, and the new on-site public water mains will need to be located in either public streets or public water line easements that are a minimum of 15' wide.

4. Any questions, comments or concerns about these projects may be directed to:
Tim Rowe, P.E., Civil Engineer
Tucson Water, New Development Section
310 W. Alameda St.
P.O. Box 27210
Tucson, AZ 85726-7210
(520) 837-2106
tim.rowe@tucsonaz.gov